Written question asked by Tom Brake (Liberal Democrat) on Wednesday, 11 January 2006, in the House of Commons. It was due for an answer on Monday, 16 January 2006. It was answered by Stephen Ladyman (Labour) on Thursday, 2 February 2006 on behalf of the Department for Transport.


Multi-modal Studies

Question
To ask the Secretary of State for Transport if he will list the schemes which arose as an outcome of multi-modal studies which have been awarded investment by his Department, broken down by (a) road construction and (b) public transport schemes and what (i) the amount awarded and (ii) the location of each scheme was in each case.
Answer

The Multi-Modal Studies were strategic transport studies which developed recommendations for implementation over the short, medium and longer term up to 2031. Many of the schemes recommended required further detailed development and appraisal work before being ready for implementation. In our responses to the Multi-Modal Studies we set out the way in which we wished to see the study recommendations taken forward by the relevant delivery agencies.The schemes recommended by the Multi-Modal Studies which have reached the stage of programme entry or equivalent with agreed funding allocations are listed in the following tables. A number of other schemes are continuing to be prepared for a decision on programme entry by the respective delivery agencies.

Highways agency trunk road schemes (targeted programme of improvements)
Multi-modal study HA TPI scheme Location Latest budget cost (£ million)
Cambridge to Huntingdon A14 Ellington to Fen Ditton Improvement Cambridgeshire 490
Access to Hastings A21 Tonbridge to Pembury Kent 65
London to South Midlands M1 Junction 6a to 10 Widening Hertfordshire 289
London to South Midlands M1 Junction 10 to 13 widening Bedfordshire 382
A1 North of Newcastle A1 Morpeth to Felton Dualling Northumberland 84
A1 North of Newcastle A1 Adderstone to Belford Dualling Northumberland 14
Tyneside Area A1/A19/A1068 Seaton Burn Junction Improvement Tyneside 29
Tyneside Area A19/A184 Testos Grade Separated Junction Tyneside 21
London to South Midlands A505 Dunstable Northern Bypass (A5 to M1 Link) Bedfordshire 48
London to South Midlands A421 Bedford to M1 Junction 13 Bedfordshire 171
London to South West and South Wales A30 Garland Cross to Chiverton Cross Cornwall 125
London to South West and South Wales A30 Temple to Higher Carblake Improvement Cornwall 41
North/South Movements in the East Midlands M1 Junction 21 to 30 widening Leicestershire, Nottinghamshire and Derbyshire 1,915
Orbit (M25) -London Orbital Transport Solutions M25 Junction 1B to 3 widening Kent 66
Orbit (M25) -London Orbital Transport Solutions M25 Junction 5 to 7 widening Surrey and Kent 214
Orbit (M25) -London Orbital Transport Solutions M25 Junction 16 to 23 widening Hertfordshire and Berkshire 496
Orbit (M25) -London Orbital Transport Solutions M25 Junction 23 to 27 widening . Hertfordshire and Essex 419
Orbit (M25) -London Orbital Transport Solutions M25 Junction 27 to 30 widening Essex 402
A453 (M1 Junction 24 to Nottingham) A453 Widening (M1 Junction 24 to A52 Nottingham) Nottinghamshire 90
London to Ipswich M25 Junction 28/A12 Brook Street Interchange Essex 8
South Coast M27 Junction 11 to 12 Climbing Lanes Hampshire 27
South Coast M27 Junction 3 to 4 Widening Hampshire 52
South Coast A27 Southerham to Beddingham Improvement East Sussex 19
South and West Yorkshire MMS M1 Junction 30 to Junction 31 Widening Yorkshire 136
South and West Yorkshire MMS M1 Junction 31 to 32 Widening Yorkshire 20
South and West Yorkshire MMS M1 Junction 32 to 34S Widening Yorkshire 139
South and West Yorkshire MMS M1 Junction 34N to 37 Widening Yorkshire 246
South and West Yorkshire MMS M1 Junction 37 to 39 Widening Yorkshire 224
South and West Yorkshire MMS M1 Junction 39 to 42 Widening Yorkshire 202
South and West Yorkshire MMS M1 Junction 31 to 32 Northbound Collector/Distributor Yorkshire 29
South and West Yorkshire MMS M62 Junction 25 to 27 Widening Yorkshire 215
South and West Yorkshire MMS M62 Junction 27 to 28 Widening Yorkshire 83
Local transport major schemes (roads and public transport)
Multi-modal study Scheme Location Estimated cost (£ million)
South Coast Bexhill to Hastings Link Road East Sussex 48.5
South East Manchester A34 Alderley Edge Bypass Cheshire 37.9
South East Manchester South East Manchester Quality Bus Corridor Greater Manchester 23
M60 Junction 18 to 12 JETTS Quality Bus Corridor Greater Manchester 26.3
West Midlands Area Red Routes (Metropolitan Area Wide) West Midlands 28
Cambridge to Huntingdon Cambridge Guided Busway Cambridgeshire 65
South and West Yorkshire A628 Cudworth Bypass Barnsley 17.2
South and West Yorkshire A57 M1 Junction 31 to Todwick Crossroads Rotherham 6.3
Other local transport plan supplementary bids
Cambridge to Huntingdon Traffic Calming of Villages close to proximity of A14 Cambridgeshire (various Villages) 4
Access to Hastings, South Coast, Orbit (M25) and Thames Valley Studies Local Transport Initiatives (these were smaller schemes from the outcome from the four Multi-Modal Studies undertaken in the South East region) South East 3.7
London to Ipswich Chelmsford Park and Ride Note: Park and Ride was recommended by the MMS in general terms Chelsmford, Essex 1.5
Norwich to Peterborough Kings Lynn Bus Station Refurbishment and Improved integration with the railway station; creation of a high quality multi-modal interchange facility at Thetford Railway station, improved bus stop infrastructure in Downham market and pedestrian and cycling signing in market towns Norfolk (Kings Lynn, Thetford, Downham Market and various Norfolk Market Towns) 1,395
A453 MMS Clifton/Silverdale Integrated Transport Measures Nottingham 0.850
(6) Supplementary LTP bid.

RailService and capacity improvements that have been implemented on the rail network have contributed to the delivery of a number of rail improvements recommended by the Multi Modal Studies. These include:

Study Rail recommendations
West Midlands to North West Conurbation (MIDMAN) and London to South Midlands West Coast Project
London to South Midlands Construction of 12 car platforms on West Coast south of Northampton -with introduction of longer trains as demand require
London to South Midlands More carrying capacity on Midland Mainline through new franchise and Route Utilisation Outputs
South Coast Introduction of new Ashford—Brighton service from December
London to South West and South Wales Capacity and bottleneck relief schemes at locations such as Probus Burngullow, Filton Junction
Thames Valley and London to South West and South Wales Introduction of new timetables on Greater Western enhancing capacity, with further enhancements as a result of the new franchise

Secondary information

Type
Written question
Reference
42712; 442 c658-62W;442 c658-62W
Session
2005-06
Related items
Multi-modal Studies
Tuesday, 7 February 2006
Written questions
House of Commons
Multi-modal Studies
Tuesday, 7 February 2006
Written questions
House of Commons
Multi-modal Studies
Tuesday, 7 February 2006
Written questions
House of Commons
Multi-modal Studies
Tuesday, 7 February 2006
Written questions
House of Commons
Show all related items (7)
Multi-modal Studies
Tuesday, 7 February 2006
Written questions
House of Commons
Multi-modal Studies
Tuesday, 7 February 2006
Written questions
House of Commons
Multi-modal Studies
Tuesday, 7 February 2006
Written questions
House of Commons
Subjects
Construction Investment Public transport Transport Roads Research
Contains statistics
Yes
Link
View this Written question on www.publications.parliament.uk