Written question asked by Alistair Carmichael (Liberal Democrat) on Wednesday, 22 March 2006, in the House of Commons. It was due for an answer on Monday, 27 March 2006. It was answered by Stephen Ladyman (Labour) on Tuesday, 28 March 2006 on behalf of the Department for Transport.


Road Improvement Costs

Question
To ask the Secretary of State for Transport pursuant to his answer to the hon. Member for Carshalton and Wallington (Tom Brake) of 19 December 2005, Official Report, columns 2318–2319W, on road improvement costs, how much compensation has been paid under part 1 of the Land Compensation Act 1973 in each case; and what other costs in each case have been incurred by the Highways Agency which are not paid to the scheme contractor.
Answer

The latest agreed budget costs for schemes in the TPI, represent the current approved estimate of the full outturn costs and include land acquisition and compensation, VAT and the cost of statutory undertaker diversions in addition to payments to the contractor/designer.No compensation has yet been paid under part 1 of the Land Compensation Act 1973, in relation to any of the projects listed. This is because such compensation can only be claimed from one year after road opening, and none of the schemes listed have reached this stage.


Secondary information

Type
Written question
Reference
61750; 444 c859W;444 c859W
Session
2005-06
Related items
Road Improvement Costs
Monday, 19 December 2005
Written questions
House of Commons
Subjects
Construction Roads
Link
View this Written question on www.publications.parliament.uk