Oral question asked in the House of Lords, by Lord Campbell of Alloway (Conservative). It was answered by Lord Falconer of Thoroton (Labour) on Monday, 24 July 2006.


Supreme Court

Question
What are the estimated cost and date for completion of the new Supreme Court.
Answer

My Lords, the capital construction costs remain as described in my Written Ministerial Statement of 14 December 2004, subject to those costs having been adjusted for inflation, and they now stand at £35.3 million. There will be additional associated costs, such as fees and furniture. Westminster City Council is currently considering a local planning application, on which it is expected to reach a decision over the Summer Recess. We do not yet know whether this decision will have an impact on the costs. Therefore, when the application has been decided, I propose to make a full report to the House, including the overall estimated costs, once Parliament returns. Subject to a successful application, it remains my intention that the UK Supreme Court should open for business in October 2009.


Secondary information

Type
Oral question
Reference
684 c1538 
Session
2005-06
Oral question type
Lead
Chamber / Committee
House of Lords chamber
Related items
Subjects
Costs Supreme Court
Contains statistics
Yes
Link
View this Oral question on www.publications.parliament.uk