Oral answer to question provided on Tuesday, 17 July 2007 in the House of Lords, by Lord Davies of Oldham (Labour).


Millennium Dome

Answer

My Lords, it is a matter of record that this large public project was completed on time, that the final cost was just 4 per cent over budget and that it was by far the most visited paying attraction in the UK with more than 80 per cent visitor satisfaction. It also helped to regenerate a wide area. However, the main lesson from the project concerns the importance of ensuring that forecasts of income from visitors and sponsors are realistic.

This is an answer to the Oral question asked on Tuesday, 17 July 2007 by Baroness Miller of Hendon (Conservative).

Question
What lessons they have learnt from their management of the Millennium Dome.

Secondary information

Type
Oral answer to question
Reference
694 c129 
Session
2006-07
Chamber / Committee
House of Lords chamber
Subjects
Millennium dome
Link
View this Oral answer to question on www.publications.parliament.uk