Freight: Grants

Question
To ask the Secretary of State for Transport what the average length of time taken to process a freight facilities grant application is; how many applicants waited (a) more than six months, (b) more than nine months and (c) more than one year in the most recent five year period for which figures are available; and if he will make a statement.
Answer

The Department for Transport has aimed to assess standard freight facilities grant (FFG) applications within four months and more complex applications within six months. However the time taken to assess applications depends on many factors, including the completeness of the initial data supporting the application. There is also the potential for further information being received from the applicant through the course of the assessment and the potential need by the Department for clarification, which inevitably takes time.In the past three years, the Department has assessed the following cases:

Year application received Cases assessed within six months Cases assessed within nine months Cases assessed within one year
2006 3 1 0
2007 3 0 0
2008 1 1 0

In addition, a further application was received in October 2008 which is currently being assessed.The process of applying for FFGs is currently being reviewed, with a view to shorten the time taken to assess applications and make the process clearer for applicants.


Secondary information

Type
Written question
Reference
487 c1600-1W; 254520
Session
2008-09
Subjects
Freight facilities grant
Contains statistics
Yes
Link
View this Written question on www.publications.parliament.uk