Written question asked by Stephen Hammond (Conservative) on Thursday, 5 March 2009, in the House of Commons. It was due for an answer on Monday, 9 March 2009. It was answered by Paul Clark (Labour) on Thursday, 12 March 2009 on behalf of the Department for Transport.


A3: Hindhead

Question
To ask the Secretary of State for Transport what his most recent estimate is of the cost of the A3 Hindhead improvement (a) with and (b) without twin-bored tunnels under the Devil's Punch Bowl; and how much is expected to come from public funds.
Answer

The latest estimate for the A3 Hindhead improvement currently being constructed is £371 million, of which, all is to come from public funds. There is no estimate for a scheme without the twin-bored tunnels under the Devil's Punch Bowl.


Secondary information

Type
Written question
Reference
489 c594W;489 c596W; 262268
Session
2008-09
Subjects
A3 Hindhead
Link
View this Written question on www.publications.parliament.uk