Skip to main content

Written question asked by Ian Taylor (Conservative) on Monday, 9 March 2009, in the House of Commons. It was due for an answer on Wednesday, 11 March 2009. It was answered by Huw Irranca-Davies (Labour) on Tuesday, 17 March 2009 on behalf of the Department for Environment, Food and Rural Affairs.


Thames Flood Barrier

Question
To ask the Secretary of State for Environment, Food and Rural Affairs what the anticipated effective life expectancy of the Thames Barrier is; and if he will commission plans to upgrade or replace the existing Thames Barrier.
Answer

The Environment Agency's Thames Estuary 2100 Project estimates that under current guidance for sea level rise (DEFRA 2006), the Thames barrier will drop below the 1 in 1,000 standard of protection around 2070.The Thames Estuary 2100 project will release its draft plan for consultation on March 31. The plan will make recommendations on what actions will be required to manage future tidal flood risk within the estuary, and when these will be required, through to the end of the century. The plan will include recommendations on the future upgrading or replacement of the Thames barrier after 2070.


Secondary information

Type
Written question
Reference
489 c1019W;489 c1021W; 263129
Session
2008-09
Subjects
Thames flood barrier
Link
View this Written question on www.publications.parliament.uk