Written question asked by Chris Huhne (Liberal Democrat) on Friday, 29 May 2009, in the House of Commons. It was due for an answer on Tuesday, 2 June 2009. It was answered by Mike O'Brien (Labour) on Monday, 8 June 2009 on behalf of the Department of Energy and Climate Change.


Wind Power: South Downs

Question
To ask the Secretary of State for Energy and Climate Change when the wind turbines in the South Downs National Park near East Meon were (a) planned and (b) offered out to tender; and which companies tendered for the project.
Answer

I am told that the Department does not hold this information. The contracting arrangements of wind farm projects are a commercial matter for the developer concerned.


Secondary information

Type
Written question
Reference
493 c729W; 277794
Session
2008-09
Subjects
Wind power South Downs
Link
View this Written question on www.publications.parliament.uk