Written question asked by Charlotte Atkins (Labour) on Tuesday, 16 March 2010, in the House of Commons. It was due for an answer on Wednesday, 24 March 2010. It was answered by Baroness Jowell (Labour) on Thursday, 8 April 2010 on behalf of the Minister for the Olympics.


Olympic Games 2012: Construction

Question
To ask the Minister for the Olympics what the cost was of building the freight facility at the main Olympic site.
Answer

The Olympic Delivery Authority (ODA) has constructed a temporary wharf on the Waterworks River for the construction phase of the programme to provide contractors with the opportunity to move material into and out of the Park by water. The construction cost of this is £1.86 million (excluding VAT), This figure includes the costs of the pontoons, moorings, pilings, hard-standing, vehicle access and river wall protection.


Secondary information

Type
Written question
Reference
508 c1513W; 323339
Session
2009-10
Subjects
Construction Olympic Games 2012