Written question asked by Michael Fallon (Conservative) on Tuesday, 10 January 2012, in the House of Commons. It was due for an answer on Monday, 16 January 2012. It was answered by Norman Baker (Liberal Democrat) on Monday, 16 January 2012 on behalf of the Department for Transport.


Swanley Railway Station

Question
To ask the Secretary of State for Transport when the improvements at Swanley railway station (a) were originally scheduled to (i) begin and (ii) be completed, (b) began and (c) are now expected to be completed.
Answer

Works at Swanley station under the Access for All and National Stations Improvement programmes are due to start on site in July 2012 and be completed by April 2013. To allow the station to be used by spectators for the Paralympics, the work has been brought forward and will start in April this year and are due to be complete by the end of July this year.


Secondary information

Type
Written question
Reference
89527; 538 c485W
Session
2010-12
Subjects
Repairs and maintenance Swanley Station
Link
View this Written question on www.publications.parliament.uk