Written question asked by Keith Hill (Labour), in the House of Commons. It was due for an answer on Monday, 8 July 1996. It was answered by John Watts (Conservative) on Monday, 8 July 1996 on behalf of the Highways Agency.


Dept of Transport;Highways Agency

Question
If he will place a copy of the main construction contract for the Newbury Bypass in the Library; what assessment he has made of and what action he is taking to ensure that Costain Group plc will meet its contractual obligations in the construction of the Newbury bypass; what estimate he has made of the costs to his Departments budget of a failure by Costain Group plc to meet its contractual obligations in the construction of the Newbury bypass. - Text of letter from Lawrie Haynes of Highways Agency.

Secondary information

Type
Written question
Reference
281 c68-9W;281 c68W; 35501;35502;35503;35504
Session
1995-96
Subjects
Contracts Construction Roads Bypasses A34 Newbury Costain Group