Skip to main content

Written question asked by Robert N Wareing (Labour), in the House of Commons. It was due for an answer on Monday, 28 October 1996. It was answered by Ray Powell (Labour) on Monday, 28 October 1996 on behalf of the Accommodation and Works Committee.


Accommodation and Works Select Committee

Question
What is the estimated cost of building and decorating work carried out to the Palace of Westminster during the Summer Recess. - Inc figs.
Answer

Mr. Wareing: To ask the Chairman of the Accommodation and Works Committee what is the estimated cost of building and decorating work carried out to the Palace of Westminster during the summer recess. [595] Sir Raymond Powell: About £17 million worth of work was carried out on the parliamentary estate during the summer recess.


Secondary information

Type
Written question
Reference
595; 284 c49W
Session
1996-97
Subjects
Costs Buildings Legislatures Palace of Westminster Repairs and maintenance
Contains statistics
Yes