Written question asked by Bob Cryer (Labour), in the House of Commons. It was due for an answer on Friday, 10 June 1988. It was answered by Peter Bottomley (Conservative) on Friday, 10 June 1988 on behalf of the Department of Transport.


Written question

Question
What is the cost of the Settle bypass currently under construction; & when completion will take place.

Secondary information

Type
Written question
Reference
134 c731W;134 c729W
Session
1987-88
Subjects
Construction Bypasses A65 Settle