Proceeding contribution from Lord Berkeley (Labour) in the House of Lords on Thursday, 13 January 2011. It occurred during Debate on Revised Draft National Policy Statement for Nuclear Power Generation, volumes I and II (EN-6).
Revised Draft National Policy Statement for Nuclear Power Generation, volumes I and II (EN-6)
My Lords, I am very pleased to be able to take part in this debate and I congratulate the Minister on bringing forward these documents and those that we discussed on Tuesday. We debated this whole process long and hard when the legislation was going through. It is good that we are able to scrutinise and consider these documents without the possibility of amending them at this stage. I declare an interest as being chairman of the Rail Freight Group and a harbour commissioner in the port of Fowey in Cornwall. The proposed nuclear power stations will probably be absolutely necessary to achieve the Government's carbon reduction commitments. I hope that Ministers, having decided to go nuclear, will be able to look at the carbon footprint of the construction and manufacture of nuclear power stations to make sure they play their part in contributing to carbon reduction. Whether one starts with uranium mining, I am not sure, but they should certainly look at construction and materials. A lot of people do not realise that in producing a tonne of cement, you produce a tonne of carbon. That is an easy calculation to remember, but it is still an awful lot of carbon. Steel probably takes even more. Then there is the question of deliveries to site; I shall come on to that. I have not seen anything in the documents that covers that, so I want to talk about it briefly this afternoon. Before I get on to that, there are a couple of things, starting in paragraph 2.10, to do with flood risks and droughts. I have been talking to people in Oldbury and Hinkley Point about whether it would be useful to bring things in by sea. I am conscious that, certainly at the Oldbury site, people are extremely concerned about the level of the tide that will be coming up the River Severn in the future and about how high they have to build. The document is silent on the design time for which they should calculate the level above the flood. It says that the design should be for the life of the power station, but it is possible to give these things extra life by upgrading them in 30 years' time or so. Even if they are decommissioned, there is a question of whether it will matter if they flood. I do not know, but I do not see the timescale for which flood risk is calculated addressed here. Do you work to a 100-year flood or a 200-year flood? In the past few weeks, we have seen some pretty frightening floods in Brazil, and in Australia following 10 years' drought, and the calculation will be different. I would feel more comfortable if something in the document was a bit more specific as to how the bidders should approach the matter and how they will be judged. Conversely, paragraph 2.10.2 talks about the risk of drought. The Minister mentioned the comments from the noble Lord, Lord Cope, about Oldbury and the high cooling towers; he has certainly talked to me about that too. It is pretty extraordinary that you need cooling towers when you are next to the sea, because the sea is not a bad source of cooling. I am told that it is because when the Severn goes out and there is no water in it at low tide, there might be a problem, but I should have thought that it would have been possible to build a tidal lake to fill up at every high tide, and to make sure that there was enough volume to provide the cooling needed until the next high tide. High tides are pretty predictable; they do not not come. They have slightly different levels sometimes, but they usually come. I hope that that will be looked at as an alternative to having any of these cooling towers at all at Oldbury, frankly. Paragraph 3.13.3 is welcome. It talks quite a lot about the impact of the construction, but construction is not seen as particularly important. The paragraph talks about the long term; the rest of it says, ““There will be a few problems during construction””. I have worked on a few big projects in my time. Transport Ministers are trying to persuade people in the Chilterns that a high-speed line is a good idea, but people get upset when new things are built near them. It would be useful to have in the document—I am not sure where—some reference to the importance of mitigating the effects of construction in terms of transport noise and everything else. From the point of view of carbon reduction, I would certainly like some reference to environmentally friendly transport such as sea or rail. You cannot use rail everywhere, but you probably can use sea in most places because these things are built by the sea. I have been doing quite a lot of work with regard to the Olympics, trying to make the construction more environmentally friendly. We have had some success in getting materials brought in by rail and river, but the process of procurement was not designed or managed nearly as well as Heathrow Airport's terminal 5. At one stage, I calculated that if the procurement and logistics had been organised, about 800,000 lorry movements into Stratford, east London, could have been saved. The same examples would apply to any major project anywhere, such as a nuclear power station. In a document such as this, some reference to minimising the carbon footprint, together with all the other mitigating effects, would be very useful. Certainly you can build quays at Oldbury and Hinkley Point to bring in materials, as we have been discussing. You could extend railway lines to those sites or you could have short railway lines, but I think that a bit more work could be done to mitigate the effects. Finally, if a railway line is to be built, it could be used to get the nuclear waste out, as such waste does not often go by road for very long distances. In conclusion, I think that this is a good document. It says all the right things, although it just needs to say a little more. However, it is an improvement on the previous document and I commend it.
Secondary information
- Type
- Proceeding contribution
- Reference
- 723 c153-5GC
- Session
- 2010-12
- Chamber / Committee
- House of Lords Grand Committee
- Subjects
- Cumbria Finance Environment protection Infrastructure Floods Kent Planning permission Planning Radioactive waste Nuclear power Nuclear fuel reprocessing Nuclear power stations Security Waste management Infrastructure Planning Commission National policy statements Mixed oxide fuel
- Link
- View this Proceeding contribution on www.publications.parliament.uk
Librarians' tools
- Timestamp
- 2025-05-18 08:18:28 +0100
- URI
- http://data.parliament.uk/pimsdata/hansard/CONTRIBUTION_700407
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/pimsdata/hansard/CONTRIBUTION_700407
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/pimsdata/hansard/CONTRIBUTION_700407