Proceeding contribution from Lord O'Neill of Clackmannan (Labour) in the House of Lords on Thursday, 13 January 2011. It occurred during Debate on Revised Draft National Policy Statement for Nuclear Power Generation, volumes I and II (EN-6).


Revised Draft National Policy Statement for Nuclear Power Generation, volumes I and II (EN-6)

My Lords, one feature of the handling of the nuclear issue has been the importance that we place on timetabling. Given that power stations will close because of exhaustion, obsolescence and, not least, changes in environmental standards, we are going to face the possibility at least of a generating gap in the middle of this decade. It is fair to say that, whatever fills that gap, we will have a radically different energy mix in generation terms from what we have at present. Certainly, when we get down to the fundamentals, it is a matter of keeping the lights on, keeping houses warm and keeping industry going. Ultimately, it will not be some alphabet soup of foreign energy companies that get the blame for the fact that the lights begin to flicker; in the final analysis, it will be the Government of whichever political complexion who will be deemed to be to blame. Therefore, it is important that we all take this process extremely seriously. Certainly, the requirements of the planning legislation, in whatever form it appears, will mean that after a proper period of debate and consultation the Government's view—whoever they are—of the best means of meeting our energy requirements as they would define them will come to both Houses for acceptance. It is quite likely that we will not agree on every jot, dot and comma, but there is an emerging consensus that nuclear has a significant part to play in what we might call a mixed or balanced energy policy basket of generating capability. Speaking as chairman of the Nuclear Industry Association, in which I declare an interest, I offer my support for the statement before us today. The Labour Government published a broadly similar statement with a few amendments, but the broad thrust from the Conservative-led Government is very similar to that of the Labour Party. Attention has been drawn to some of the differences. Certainly, there will be changes in the planning process. I do not like all the changes and I think that they are open to the threat of unnecessary delay, but I do not really see the IPC and its successor being that much at variance over the manner in which they ultimately handle the planning issues. However, before we even get to that stage, there is the question of the sites. Already this afternoon we have had some debate about Dungeness. When we last discussed this matter, the debate was heavily influenced by the intervention of the noble Baroness, Lady Young of Old Scone. I remind the Minister that a scone, pronounced ““scon””, is something that you eat, whereas Scone, pronounced ““scoon””, used to be the palace of the Scottish kings—not that I am a great supporter of Scottish kings. Nevertheless, I feel a certain responsibility to help English people with the pronunciation of a language which they have sought to appropriate. It is the old story: it is not us who have the accent but you, as I am sure the noble Lord on the other side will agree. I notice that the Minister is keeping an open mind on this issue. We have to be careful about the ““latest report syndrome””. If we keep chasing every hare down every hole, we get virtually nowhere when decisions have to be taken. We are talking today about eight out of a potential 10 stations. It should be borne in mind that if we make use of five of the existing sites, we will have replaced all the existing nuclear capability in the UK. Therefore, stations 6, 7 and 8 will be additional generating capability, probably in the order of 3 gigawatts of power or perhaps even more depending on the type of reactor used. That seems to be regarded by the potential generators as the minimum. We are therefore talking about quite a sizeable increase in the nuclear contribution by 2025 if everything goes through. By 2023 or 2024, other sites may need to be considered. I would like to think that that is the case, because the sites currently envisaged for development are achieved on the basis of sound financial considerations and that they meet their targets on time, and of course that they do it safely. If each of those boxes is ticked, it seems self-evident that there will be other people, or perhaps the existing players, wishing to take advantage of alternative sites. As I have said in other debates on this topic, I would hope that at least one of the two sites in Scotland will become available for UK plc. With every week that passes, I am more confident that we will see the end of the anti-nuclear nationalist lot in the Scottish Parliament and a coalition of some kind or another which is likely to be more sympathetic to the exploitation of at least one—I hope both—of the sites at Hunterston and Torness. I hope that the Minister in presenting this document today is not saying that this is the last word and that, at an appropriate time, he will be prepared to look afresh at additional sites, or perhaps the two that have been suggested in Cumbria—if some of the concerns there can be met. Indeed, I hope that he will look at whether sites of other power stations can be used. Let us face it, one of the great arguments for the placement of nuclear power stations on existing sites is that there is public tolerance and technical capability, and there are wires. If there are wires and there are people who are used to running power stations, you meet at least almost two of the three or four necessary criteria. We may well find that there are major stations which currently burn coal whose sites could be used for nuclear purposes if that was appropriate. As someone who represented a former mining area when I was an MP, I know of the unemployment levels, because we had never been able to replace the kind of work that was made available by the coal industry at the same rates of pay and with the same job satisfaction. To many people it would seem pretty hellish work, but for the guys who worked there it was something in which they took pride, in terms of not just their physical prowess but their technical ingenuity. It would be wrong for us to try to portray this as the last word on the subject. I am asking for flexibility, but it is appropriate to emphasise that we will need consistency in planning. When people go to the expense of making a planning application, as has been alluded to already, they should have confidence that it will be handled in a consistent, speedy but nevertheless rigorous manner, because we have to balance the needs both of the investor and the general public. I have concerns about the change from the IPC to the Major Infrastructure Planning Unit, in respect largely of ministerial interference. However, we can discuss that another day, because we are dealing here with the broad guidelines that have to be followed. At the moment, there is not so much public concern about what seems to be the rather Whitehall issue, you might say, of the planning arrangements. There are always issues of public anxiety relating to safety of the environment. It is reassuring to see in the document a confidence expressed by the Government that they have already dealt with the funding of waste management. The noble Baroness, Lady Parminter, referred to that. My understanding is that an agreement has been arrived at as to the cost per unit of electricity under the new arrangements, in respect of what has to be made available for the handling of waste, so the financial issue has been taken care of. On the technical issue, the answers are available and are being tried—one can only use the word ““tried””, because they are not yet complete—in Scandinavia, including Sweden and Finland. They are also being tried in parts of North America, although there the vagaries of the federal system of government, the states' rights and what have you mean that in some areas it may go a bit more slowly. The fact is that people are handling waste and making preparations to store it. I know that the noble Lord, Lord Broers, will speak; the noble Lord, Lord Jenkin, and I were members of the Select Committee. We were concerned about CoRWM and both Governments being relaxed—complacent even—about the fact that it is a long-term issue, and that we will sort it out eventually. My noble friend Lord Davies made the valid point that we have waste that is not just a liability but can become an asset. That will obviously be dealt with elsewhere than this document, partly because the Government are a wee bit frightened of talking about reprocessing in this context. However, the fuelling of the generation has to be part of the answer to the nuclear issue. I understand that some of the contracts at Sellafield have to be reconsidered and renegotiated in 2012. The issue is not within our concerns today, but the rather relaxed approach that CoRWM adopted when it presented evidence to the Science and Technology Committee on its future plans was that it is 35 years or thereabouts before it really needs to get down to business on this. A lot of us think that is far too long a period and that the Government have to get a grip on the issue a lot earlier. These are comparatively small points, but they have to be dealt with in terms of giving signals to the public. I was a bit concerned when the Government said that they would look again at the whole question of the national policy statement. I thought again about it, and recognised that public concern about nuclear is such that we have what you might say is grudging support for nuclear power in the UK. As we pass justification so overwhelmingly in the other House, and with the broad consensus that was evident in the Chamber when we debated it here, and as we pass each milestone and there is no application for judicial review, so we clearly see the case for nuclear becoming ever more accepted by the people. Therefore, I welcome the statement today. I see it as a means whereby the public can be increasingly reassured and investors will feel emboldened to make application for the new stations that we know we require. On this side of the House we are here not just to support issues, but to oppose on occasions, and it is fair to say that we will come back and haunt the Government on some of them. I have certain qualifications but, on the broad approach today, I am happy that this is a good step forward, which the House and the country will come to applaud.


Secondary information

Type
Proceeding contribution
Reference
723 c165-8GC 
Session
2010-12
Chamber / Committee
House of Lords Grand Committee
Subjects
Cumbria Finance Environment protection Infrastructure Floods Kent Planning permission Planning Radioactive waste Nuclear power Nuclear fuel reprocessing Nuclear power stations Security Waste management Infrastructure Planning Commission National policy statements Mixed oxide fuel