Skip to main content

Written question asked by Andrew Gwynne (Labour) on Monday, 2 March 2015, in the House of Commons. It was due for an answer on Wednesday, 4 March 2015. It was answered by John Hayes (Conservative) on Monday, 9 March 2015 on behalf of the Department for Transport.


M60: M67

Question

To ask the Secretary of State for Transport, if his Department will make an assessment of progress on the M60/M67 interchange pinch point work.

Answer

This scheme is now substantially complete in that all road layout changes are in place with the associated benefits for drivers now realised. Landscaping works around the junction will be undertaken later this month.

During the course of the works there has been a constant assessment of progress by means of weekly collaboration and planning meetings held between the Highways Agency and its maintenance contractor’s project delivery team.


Secondary information

Type
Written question
Reference
225870
Session
2014-15
Subjects
Repairs and maintenance M60 M67
Link
View this Written question on www.parliament.uk