Written question asked by Oliver Heald (Conservative) on Tuesday, 1 December 2015, in the House of Commons. It was due for an answer on Thursday, 3 December 2015. It was answered by Andrew Jones (Conservative) on Wednesday, 9 December 2015 on behalf of the Department for Transport.
A1(M): Hertfordshire
- Question
-
To ask the Secretary of State for Transport, pursuant to the Answer of 15 June 2015 to Question 2065, what progress has been made on the design and planning of the A1 (M) widening scheme; when that process is expected to be completed; and if he will make a statement.
- Answer
-
The Department for Transport published the Roads Investment Strategy in December 2014, which set out plans to invest £15 billion in England’s motorways and major A roads between 2015/16 and 2020/21. Highways England subsequently published a Delivery Plan in March 2015, which outlined how this investment would be delivered across various projects. The Delivery Plan includes the introduction of Smart Motorways on the A1(M) between Junctions 6 and 8 will provide improved capacity and better access, and should unlock much of the growth potential around Stevenage.
The scheme is expected to start design development works early in 2016 and to commence construction by March 2020 at the latest, subject to determining the right operational solution and achieving a solution that is value for money.
Secondary information
- Type
- Written question
- Reference
- 18426
- Session
- 2015-16
- Related items
- Subjects
- Hertfordshire A1 (M)
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2022-09-27 16:51:40 +0100
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2015-16/18426
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2015-16/18426
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2015-16/18426