Written question asked by Tom Pursglove (Conservative) on Tuesday, 15 March 2016, in the House of Commons. It was due for an answer on Thursday, 17 March 2016. It was answered by Andrew Jones (Conservative) on Tuesday, 22 March 2016 on behalf of the Department for Transport.


A45

Question

To ask the Secretary of State for Transport, what assessment his Department has made of progress on the planned improvements to the Chowns Mill roundabout.

Answer

We have completed a number of technical surveys and are carrying out preliminary design activities for the project. A public engagement event to seek views and opinions from local residents and businesses is planned for Autumn/Winter 2016. We anticipate that works will start in late 2019. At this very early stage of planning the project, we expect the construction phase to last around 18 months.


Secondary information

Type
Written question
Reference
31141
Session
2015-16
Subjects
Repairs and maintenance A45