Written question asked by Tony Lloyd (Labour) on Monday, 26 February 2018, in the House of Commons. It was due for an answer on Wednesday, 28 February 2018. It was answered by Jesse Norman (Conservative) on Monday, 5 March 2018 on behalf of the Department for Transport.
M60: Repairs and Maintenance
- Question
-
To ask the Secretary of State for Transport, what assessment has been made of the efficacy of the working practices relating to the smart motorway construction work on the westbound carriageway of the M60; and if he will make a statement.
- Answer
-
The M60 J8 to M62 J20 is a busy stretch of urban motorway and due to the complexities this scheme presented, it was became clear that creating long lengths of roadworks for the whole delivery of the scheme was not practical, and that phasing the works was a more appropriate approach. This assessment of working practices is currently being shared with future smart motorway projects.
Secondary information
- Type
- Written question
- Reference
- 129652
- Session
- 2017-19
- Subjects
- Repairs and maintenance M60
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2018-03-05 09:22:17 +0000
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2017-19/129652
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2017-19/129652
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2017-19/129652