Skip to main content

Written question asked by Mike Gapes (Labour) on Thursday, 20 December 2018, in the House of Commons. It was due for an answer on Tuesday, 8 January 2019. It was answered by Andrew Jones (Conservative) on Monday, 14 January 2019 on behalf of the Department for Transport.


Crossrail Line

Question

To ask the Secretary of State for Transport, what recent estimate he has made of the total cost of Crossrail.

Answer

The anticipated final costs of the Crossrail project are yet to be confirmed. It is expected the project will be completed within the funding envelope of £17.6bn. The Department is working with Transport for London, for whom Crossrail Limited is a wholly-owned subsidiary.


Secondary information

Type
Written question
Reference
204371
Session
2017-19
Subjects
Costs Elizabeth line
Link