Written question asked by Jack Lopresti (Conservative) on Tuesday, 16 July 2019, in the House of Commons. It was due for an answer on Thursday, 18 July 2019. It was answered by Andrew Jones (Conservative) on Monday, 22 July 2019 on behalf of the Department for Transport.


Severn Beach Line

Question

To ask the Secretary of State for Transport, what is the cost to the public purse is for the maintenance work on the Severn Beach line planned for July and August 2019; and what additional maintenance work is planned for that line.

Answer

Network Rail’s total allocated budget for the maintenance work on the Severn Beach line planned for July and August 2019 is approximately £700,000. The only additional maintenance work planned at present is ongoing track renewal work.


Secondary information

Type
Written question
Reference
277704
Session
2017-19
Subjects
Repairs and maintenance Severn Beach line
Contains statistics
Yes
Link
View this Written question on www.parliament.uk