Written question asked by Yasmin Qureshi (Labour) on Thursday, 25 July 2019, in the House of Commons. It was due for an answer on Tuesday, 3 September 2019. It was answered by Edward Argar (Conservative) on Tuesday, 3 September 2019 on behalf of the Ministry of Justice.


Probate

Question

To ask the Secretary of State for Justice, what the average waiting time was between the application for and the granting of probate in each of the last 24 months for which HM Courts and Tribunals Service keeps records.

Answer

Official statistics are not published on the average length of time from receipt of the application to the issue of a grant of probate and letters of administration. HMCTS internal management information, which is not subject to the rigorous quality assurance processes of official statistics, has been used to show the following average times from receipt of an application to a grant being issued per month over the last 24 months and each of the last 10 years:

Month and year

Average Weeks to grant issued

July 2017

3

August 2017

3

September 2017

3

October 2017

3

November 2017

3

December 2017

3

January 2018

3

February 2018

3

March 2018

3

April 2018

3

May 2018

3

June 2018

3

July 2018

3

August 2018

3

September 2018

3

October 2018

3

November 2018

3

December 2018

3

January 2019

2

February 2019

2

March 2019

3

April 2019

2

May 2019

6

June 2019

9

Year

Average Weeks to grant issued

2008

3

2009

3

2010

3

2011

4

2012

3

2013

4

2014

4

2015

4

2016

3

2017

3

2018

3

These figures do not include cases which are waiting for a grant to be issued. The data from April 2019 to June 2019 have been extracted from the HMCTS Reform Core Case Data system, which is a new system in active development, and may not be directly comparable with figures for earlier periods. All figures, especially those for April 2019 to June 2019, are provisional and subject to revision.

Some grants are experiencing delays of between four and six weeks outside of our targets as a result of significant increases in work during March and April and some technology issues which have now been resolved. We have recruited more staff and are now issuing in excess of 1,000 grants a day, which is bringing waiting times down further.


Secondary information

Type
Written question
Reference
282278
Session
2017-19
Grouped for answer
Yes
Subjects
Administrative delays Probate HM Courts and Tribunals Service
Contains statistics
Yes
Link
View this Written question on www.parliament.uk