Written question asked by Vicky Foxcroft (Labour) on Thursday, 11 February 2021, in the House of Commons. It was due for an answer on Monday, 22 February 2021 (named day). It was answered by Christopher Pincher (Conservative) on Monday, 22 February 2021 on behalf of the Ministry of Housing, Communities and Local Government.


Buildings: Insulation

Question

What steps he is taking to ensure that all residential buildings with unsafe cladding are remediated.

Answer

Almost 95 per cent of all high-rise buildings identified at the beginning of last year with unsafe Aluminium Composite Material (ACM) cladding have now been remediated or have works underway.

The Government has announced a further £3.5 billion for the remediation of unsafe cladding on high rise buildings of 18 metres and above, in addition to the £1.6 billion we have already provided. Through an additional package we will also now provide a generous financing scheme to allow buildings of 11-18 metres in height to access finance for remediation of unsafe cladding. Leaseholders will pay no more than £50 per month towards this.


Secondary information

Type
Written question
Reference
912397
Session
2019-21
Question not reached
Yes
Notes
Date tabled listed on website as 22 Feb 2021
Subjects
Buildings Fire prevention Insulation Repairs and maintenance
Link
View this Written question on questions-statements.parliament.uk