Written question asked by Nigel Adams (Conservative) on Friday, 17 February 2023, in the House of Commons. It was due for an answer on Tuesday, 21 February 2023. It was answered by Rebecca Pow (Conservative) on Wednesday, 22 February 2023 on behalf of the Department for Environment, Food and Rural Affairs.
Flood Control: Tadcaster
- Question
-
To ask the Secretary of State for Environment, Food and Rural Affairs, when she expects construction work to commence on the Flood Alleviation Scheme for Tadcaster.
- Answer
-
The Environment Agency has accelerated work on the Tadcaster Flood alleviation scheme following flooding in 2020. This includes completion of small scale work to existing flood defences and accelerating modelling, feasibility and design, alongside ongoing community engagement. Further formal public engagement will take place in March 2023. This will influence the Outline Business Case which is scheduled for submission in April 2023. The application for planning permission and detailed design will follow and construction is still scheduled to commence in early 2024.
Secondary information
- Type
- Written question
- Reference
- 146942
- Session
- 2022-23
- Subjects
- Construction Flood control Tadcaster
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2023-06-24 07:35:23 +0100
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2022-23/146942
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2022-23/146942
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2022-23/146942