Written question asked by Mike Amesbury (Labour) on Monday, 13 May 2024, in the House of Commons. It was due for an answer on Wednesday, 15 May 2024. It was answered by Lee Rowley (Conservative) on Tuesday, 21 May 2024 on behalf of the Department for Levelling Up, Housing and Communities.
High Rise Flats: Insulation
- Question
-
To ask the Secretary of State for Levelling Up, Housing and Communities, what information his Department holds on the number of buildings between 11 and 18 metres in height with aluminium composite material cladding that have not started remediation works.
- Answer
-
75 buildings between 11 and 18 metres have been identified as having ACM on the External Wall System and require remediation. 26 have started work and 49 have not. We will continue to push for further progress on this, and all remediation, at the earliest opportunity.
Secondary information
- Type
- Written question
- Reference
- 25936
- Session
- 2023-24
- Subjects
- Fire prevention Insulation Repairs and maintenance High rise flats Composite materials
- Contains statistics
- Yes
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2024-05-21 14:59:14 +0100
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2023-24/25936
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2023-24/25936
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2023-24/25936