Written question asked by Barry Gardiner (Labour) on Wednesday, 12 November 2025, in the House of Commons. It was due for an answer on Monday, 17 November 2025. It was answered by Michael Shanks (Labour) on Friday, 21 November 2025 on behalf of the Department for Energy Security and Net Zero.


Drax Power Station: Timber

Question

To ask the Secretary of State for Energy Security and Net Zero, if he will steps he will take to prevent Drax power station from burning old growth forest wood in its power station between now and 2027.

Answer

We work closely with Ofgem on monitoring environmental regulations and forestry practices in areas where biomass is sourced to ensure the sustainability of the feedstock coming to the UK.

In October 2023 Drax adopted a policy of not sourcing material directly from old growth areas in British Columbia for Drax Power Station in Selby. As a result of Ofgem’s investigation, Drax are currently conducting a global review of their supply chain through an independent auditor. We will carefully consider the results of this audit.

From 2027 onwards, the new Low Carbon Dispatchable Contract for Difference strengthens sustainability requirements by ensuring no subsidy is paid for electricity generated from primary material harvested from primary forest or old growth areas.


Secondary information

Type
Written question
Reference
90099
Session
2024-26
Related items
Drax Power Station: Timber
Tuesday, 9 December 2025
Written questions
House of Commons
Subjects
Timber Drax power station
Link
View this Written question on www.parliament.uk