Written question asked by Steve Barclay (Conservative) on Monday, 1 June 2026, in the House of Commons. It was due for an answer on Wednesday, 3 June 2026. It was answered by Josh MacAlister (Labour) on Tuesday, 9 June 2026 on behalf of the Department for Education.


Free Schools

Question

To ask the Secretary of State for Education, what her planned timeline is for the delivery of new free schools approved in principle, including the (a) key stages from approval to opening, (b) typical duration of each stage and (c) factors impacting delivery times; and what the status is of the proposed Lime Academy school in March, Cambridgeshire, including (i) progress on site identification, (ii) anticipated pupil capacity, (iii) estimated capital cost and (iv) expected opening date.

Answer

New free school projects that are centrally delivered by the department typically progress through six key stages: pre‑feasibility (including finding a suitable site), feasibility, procurement, design and planning, construction and handover, and post‑completion use. Utilising delivery data from the past 5 years, average durations are up to a year for feasibility, 18 months for procurement, and 18-24 months for construction. Delivery timelines can be impacted by a number of factors such as securing a suitable site and constraints, planning or environmental issues, and market conditions affecting costs and materials.

For Lime Academy March, a site off Kingswood Road has been identified and lease terms are under negotiation. The school is planned to provide 210 places for pupils aged 2–19. Capital costs are not yet confirmed at this stage. Current assumptions indicate an opening date no earlier than September 2029.


Secondary information

Type
Written question
Reference
5326
Session
2026-27
Subjects
Free schools
Link
View this Written question on www.parliament.uk