Written question asked by Lord German (Liberal Democrat) on Monday, 12 March 2018, in the House of Lords. It was due for an answer on Monday, 26 March 2018. It was answered by Lord Henley (Conservative) on Monday, 26 March 2018 on behalf of the Department for Business, Energy and Industrial Strategy.
Hinkley Point C Power Station
- Question
-
To ask Her Majesty's Government what is the expected total number of tons of waste material arising from the construction of the new Hinkley Point power station to be deposited in the Cardiff Grounds.
- Answer
-
The amount of dredge material requested by the applicant in the marine licence application is for a maximum of 280,000 tonnes. The original figure was higher than this, however the licence holder now requires dredging from a smaller area.
Secondary information
- Type
- Written question
- Reference
- HL6235
- Session
- 2017-19
- Subjects
- Construction Waste disposal Severn estuary Hinkley Point C power station
- Contains statistics
- Yes
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2023-05-24 19:58:04 +0100
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/lords/2017-19/HL6235
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/lords/2017-19/HL6235
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/lords/2017-19/HL6235