Written statement made by Kwasi Kwarteng (Conservative) on Thursday, 23 January 2020 in the House of Commons, on behalf of the Department for Business, Energy and Industrial Strategy.


Offshore Wind Energy Infrastructure Projects

This Statement concerns applications made by Orsted Hornsea Project Three (UK) Limited, Norfolk Vanguard Limited and Vattenfall Wind Power Limited for development consent for the installation, operation and maintenance of the proposed Hornsea Project Three, Norfolk Vanguard and Thanet Extension offshore wind farms respectively, their related offshore infrastructure off the coast of Norfolk and Kent and their related onshore electrical connections within those counties.

Under section 107(1) of the Planning Act 2008, the Secretary of State must make a decision on an application within three months of the receipt of the Examining Authority’s report unless exercising the power under section 107(3) of the Planning Act 2008 to set a new deadline. Where a new deadline is set, the Secretary of State must make a Statement to Parliament to announce it.

The statutory decision deadline for the Hornsea Project Three offshore wind farm application was re-set by Written Ministerial Statement on 8 October 2019. However, following a request by Orsted Hornsea Project Three (UK) Limited on 12 December 2019 for an extension of the period of six weeks by which to provide additional information to the Secretary of State, to 14 February 2020, the Secretary of State has decided to re-set the decision deadline to 1 June 2020 to allow that information to be received and assessed including any further consultation required.

The deadline for the decision on the Norfolk Vanguard offshore wind farm was 10 December 2019 and the deadline for the Thanet Extension offshore wind farm was 11 December 2019. The Secretary of State has decided to set a new deadline of 1 June 2020 for deciding these two applications to allow further information to be provided and assessed including any further consultation required.

The decision to set the new deadlines for these three applications is without prejudice to the decisions on whether to grant or refuse development consents for them.


Secondary information

Type
Written statement
Reference
HCWS57 
Session
2019-21
Related items
Energy Planning Project
Tuesday, 8 October 2019
Written statements
House of Commons
Energy Infrastructure Planning Projects
Thursday, 25 June 2020
Written statements
House of Commons
Subjects
Kent Planning permission Norfolk Seas and oceans Wind power Ørsted Vattenfall
Legislation
Planning Act 2008
Link
View this Written statement on www.parliament.uk