Written question asked by Ian Lucas (Labour) on Wednesday, 12 February 2014, in the House of Commons. It was due for an answer on Monday, 24 February 2014 (named day). It was answered by Jeremy Wright (Conservative) on Tuesday, 25 February 2014 on behalf of the Ministry of Justice.


Prisons: Wrexham

Question

(3) when his Department plans to make a decision on who will run the new prison in Wrexham;

Ian Lucas:

Answer

The Ministry of Justice plans to appoint a prime contractor to build the prison in spring 2014 with work on site beginning in summer 2014. The prison is expected to be fully operational by late 2017.

The new prison will cost around £250 million to construct and will be Ministry of Justice funded. However, the Ministry of Justice is still in the procurement phase and therefore estimates of spending in each of the financial years are commercially sensitive.

The Ministry of Justice is considering a full range of options relating to the operation of the new prison.


Secondary information

Type
Written question
Reference
188357; 576 cc316-7W
Session
2013-14
Subjects
Prisons Wrexham
Link
View this Written question on www.publications.parliament.uk