To ask the Secretary of State for Transport, what the cost was of dredging Ramsgate port for ferry access in relation to the failed Seaborne freight contract; and who paid for that dredging.
To ask the Secretary of State for Transport, what the cost was of dredging Ramsgate port for ferry access in relation to the failed Seaborne freight contract; and who paid for that dredging.
The Government is not party to this dredging contract and so precise information about its cost is not held centrally.
To ask Her Majesty's Government how much they have spent or committed, in staff and consultant costs, on work related to (1) their contract with Seaborne Freight, and (2) the dredging of Ramsgate harbour.
To ask Her Majesty's Government how much they have spent or committed, in staff and consultant costs, on work related to (1) their contract with Seaborne Freight, and (2) the dredging of Ramsgate harbour.
The contract awarded to Seaborne was part of a broader procurement exercise to secure additional freight capacity after Brexit, wherein nine companies were approached and contracts were awarded to three. Due to the complexity of disaggregating the data from related contingency planning, the precise staff and consultancy time involved with Seaborne, and associated discussions on Ramsgate dredging, could be obtained only at disproportionate cost.
To ask the Secretary of State for Transport, what funds have been allocated to the dredging operations at Ramsgate Port.
To ask the Secretary of State for Transport, what funds have been allocated to the dredging operations at Ramsgate Port.
The Department has not allocated specific funding for dredging work at Ramsgate.
To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the Answer on 15 January 2019 to Question 207205 on Dredging of the Port of Ramsgate, whether the Marine Management Organisation have granted a license to the Port of Ramsgate for the dredging of the port...
To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the Answer on 15 January 2019 to Question 207205 on Dredging of the Port of Ramsgate, whether the Marine Management Organisation have granted a license to the Port of Ramsgate for the dredging of the port...
Under section 75 of the Marine and Coastal Access Act, certain activities by a harbour authority (or on behalf of one), within their area, are exempt from requiring a marine licence if they have a local act or a harbour order (the Ramsgate Corporation Act 1934 is the relevant local act in this case).
As a result of the dredging activity, referenced within the answer provided on 15 January 2019 to Question 207205, no arisings are being physically excavated during the dredging work and there is no material which requires disposal. The Marine Management Organisation (MMO) has not therefore granted a licence for the specific works being undertaken.
The MMO did issue a separate marine licence (L/2016/00086/2) on 18 March 2016 for ongoing maintenance and navigational dredging to the Port of Ramsgate which licences activity at the port until 2026.
To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the Answer on 15 January 2019 to Question 207205 on dredging of the Port of Ramsgate, whether Natural England were informed of the Environmental Impact Assessment conducted by the Port of Ramsgate prior to the dredging...
To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the Answer on 15 January 2019 to Question 207205 on dredging of the Port of Ramsgate, whether Natural England were informed of the Environmental Impact Assessment conducted by the Port of Ramsgate prior to the dredging...
From discussions with the Port of Ramsgate and its owner, Thanet District Council, Natural England (NE) understands that the dredging undertaken at the start of this year is considered to be maintenance dredging and as such is covered by previous environmental assessments.
To ask Her Majesty's Government whether written ministerial direction for expenditure on the contingency planning for a no deal Brexit was requested, in particular for (1) contracting with shipping lines and port operators to operate additional services, (2) developing the port of Ramsgate, (3) the provision of ferries, and (4) any...
To ask Her Majesty's Government whether written ministerial direction for expenditure on the contingency planning for a no deal Brexit was requested, in particular for (1) contracting with shipping lines and port operators to operate additional services, (2) developing the port of Ramsgate, (3) the provision of ferries, and (4) any...
No such direction has been required for any of these purposes.
To ask Her Majesty's Government which company received the award to dredge the port of Ramsgate; what is the value and completion date of that contract; where the resulting spoil will be dumped; and what are the dates on which the necessary dredging and dumping licences for this work were issued.
To ask Her Majesty's Government which company received the award to dredge the port of Ramsgate; what is the value and completion date of that contract; where the resulting spoil will be dumped; and what are the dates on which the necessary dredging and dumping licences for this work were issued.
The Government is not a party to this contract and so this information is not held centrally. Works in ports and harbours are matters for the relevant authority and must comply with the relevant regulatory regimes.
To ask Her Majesty's Government what level of subsidy they are providing, or plan to provide, towards the cost of dredging work in the harbour area of Ramsgate.
To ask Her Majesty's Government what level of subsidy they are providing, or plan to provide, towards the cost of dredging work in the harbour area of Ramsgate.
Infrastructure work is necessary to enable the port to resume Ro-Ro services. Thanet Council is in discussion with both the Department and Seaborne Freight to finalise the funding arrangements for the infrastructure works at the port, and vital dredging work has already started.
To ask the Secretary of State for Transport, what estimate he has made of the cost of dredging for the Port of Ramsgate; and whether that cost is included in the funding of the contract awarded to Seaborne Freight.
To ask the Secretary of State for Transport, what estimate he has made of the cost of dredging for the Port of Ramsgate; and whether that cost is included in the funding of the contract awarded to Seaborne Freight.
I refer the Hon Member to the answer I gave to UIN 205175.
To ask Her Majesty's Government whether they have carried out an environmental impact assessment of the current dredging of the channel at the Port of Ramsgate; if so, whether, and when, the Environment Agency evaluated and accepted that impact assessment; and when approval was given for the dredging to begin.
To ask Her Majesty's Government whether they have carried out an environmental impact assessment of the current dredging of the channel at the Port of Ramsgate; if so, whether, and when, the Environment Agency evaluated and accepted that impact assessment; and when approval was given for the dredging to begin.
The Environment Agency was consulted by the Marine Management Organisation on the application from Ramsgate Royal Harbour for the current dredging project at the Port of Ramsgate, on the 10 December 2015.
The application included an environmental impact assessment and the Environment Agency submitted comments on the 22 December 2015.
The Environment Agency accepted the proposal with the condition that material deposited within European Union bathing waters is only deposited outside the European Union bathing season.
The dredging activity does not put at risk the Water Framework Directive, therefore there is not a significant risk to the environment.
Permission was given for the activity by the Marine Management Organisation on the 29 March 2016.
To ask the Secretary of State for Transport, what funding his Department has provided Thanet Council to (a) dredge and (b) upgrade Ramsgate port by March 2019.
To ask the Secretary of State for Transport, what funding his Department has provided Thanet Council to (a) dredge and (b) upgrade Ramsgate port by March 2019.
I refer the Honourable Member to the answer I gave to PQ 205175.
To ask the Secretary of State for Environment, Food and Rural Affairs, whether Natural England has made a Habitat Regulation Assessment prior to the dredging of the Port of Ramsgate.
To ask the Secretary of State for Environment, Food and Rural Affairs, whether Natural England has made a Habitat Regulation Assessment prior to the dredging of the Port of Ramsgate.
In 2010/2011, Natural England (NE) worked with Ramsgate Harbour on environmental assessment and monitoring of their water injection dredging activities, including a Habitats Regulations Assessment of the activity undertaken at that time. After noting reports that dredging was taking place in order to prepare the port for expansion via water injection, NE have contacted the port directly to clarify what dredging is being undertaken, including volumes and locations. NE have also been in touch with the Marine Management Organisation (MMO) to clarify under which powers the port are undertaking this activity and whether an MMO licence would be required.
To ask the Secretary of State for Transport, what Environment Impact Assessment has been undertaken by Seaborne Freight prior to the dredging of the port of Ramsgate.
To ask the Secretary of State for Transport, what Environment Impact Assessment has been undertaken by Seaborne Freight prior to the dredging of the port of Ramsgate.
Work undertaken at ports, including compliance with any regulatory standards, is a matter for the relevant port authorities.
To ask the Secretary of State for Transport, what (a) infrastructure and (b) dredging work is required at the Port of Ramsgate to enable the operation of ferry services contracted by his Department; and what (a) private and (b) public institutions will fund those works.
To ask the Secretary of State for Transport, what (a) infrastructure and (b) dredging work is required at the Port of Ramsgate to enable the operation of ferry services contracted by his Department; and what (a) private and (b) public institutions will fund those works.
Maintenance dredging is currently in progress. Additionally, limited works are needed to restore the readiness of the port for regular ro-ro services, including appropriate Border Force facilities. Seaborne and my Department are working closely with Thanet Council to ensure that the Port will be ready to accept new services.
To ask the Secretary of State for Environment, Food and Rural Affairs, what assessment he has made of the level of destruction and damage caused by scallop dredging; and if he will review that practice in order to limit its potentially detrimental effects..
To ask the Secretary of State for Environment, Food and Rural Affairs, what assessment he has made of the level of destruction and damage caused by scallop dredging; and if he will review that practice in order to limit its potentially detrimental effects..
A number of studies have been carried out over the years by a variety of research bodies and individuals, which have looked specifically at the impacts of dredging on the marine environment.
For example, in 2015 the Government funded a three-phase project which is considering the impacts of towed fishing gears on mobile sediments against the background of natural variability. The report of the first phase of this project is available here (Natural variability phase 1 report).
There are a number of management measures in place, both nationally and locally, which are aimed at reducing the impact of dredging on the marine environment. Measures are reviewed regularly to ensure they remain effective and enforceable. This will continue as we work to ensure our future fisheries management is robust and effective in protecting the sustainability of our fisheries and the marine environment.
To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the Answer of 13 December 2017 to Question 118084, on Dredging, what steps he has taken to ensure that works relating to the development of the Hinkley B site comply with the London Convention 1972.
To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the Answer of 13 December 2017 to Question 118084, on Dredging, what steps he has taken to ensure that works relating to the development of the Hinkley B site comply with the London Convention 1972.
The Secretary of State is the appropriate licensing authority for the English inshore and offshore regions, although most of the Secretary of State’s licensing functions have been delegated to the Marine Management Organisation (MMO) under the Marine and Coastal Access Act 2009 (MCAA). Under Section 71(6) of the MCAA the MMO is required to comply with international law when exercising its licensing functions, including the London Protocol 1996. This Protocol was adopted in 1996 to modernise the London Convention 1972.
The MMO has issued one licence for maintenance activities at Hinkley Point B for the removal of sand and cobble material along the base of the sea wall, in order to keep the power station’s surface water drains clear. The licence is valid between 2015 and 2025, and allows for removed material to be deposited or ‘spread’ across a beach located to the east of Hinkley Point B.
Any dredging activities associated with the original construction of Hinkley Point B station would have been considered by the relevant regulator at the time of the application.
To ask Mr Chancellor of the Exchequer, how many people received an exemption from landfill tax for dredging waste in (a) 2015-16, (b) 2016-17 and (c) 2017-18.
To ask Mr Chancellor of the Exchequer, how many people received an exemption from landfill tax for dredging waste in (a) 2015-16, (b) 2016-17 and (c) 2017-18.
HMRC landfill tax returns do not require taxpayers to specify which relief applies to material that is not subject to tax. It is therefore not possible to establish how many taxpayers benefitted from a particular exemption. HMRC does not require this level of detail because it would place a disproportionate administrative burden on business.
To ask the Secretary of State for Environment, Food and Rural Affairs, what process his Department undertook to ensure that UK has complied fully with OSPAR guidance in issuing the dredge and disposal permit Marine Licence 12/45/ML.
To ask the Secretary of State for Environment, Food and Rural Affairs, what process his Department undertook to ensure that UK has complied fully with OSPAR guidance in issuing the dredge and disposal permit Marine Licence 12/45/ML.
Marine Licence 12/45/ML was issued by Natural Resources Wales, which is a matter for the Devolved Administration.