To ask the Secretary of State for Education, whether her Department has taken steps to recover costs incurred to the public purse as a result of poor workmanship in cases of school buildings constructed by Caledonian Modular that were found to be structurally unsound.
To ask the Secretary of State for Education, whether her Department has taken steps to recover costs incurred to the public purse as a result of poor workmanship in cases of school buildings constructed by Caledonian Modular that were found to be structurally unsound.
The department publishes contract values when available on Contracts Finder, which is available at: https://www.gov.uk/contracts-finder. In addition, the department publishes capital costs for all free schools on GOV.UK once all works are completed and costs are finalised. Once at that point, the department will action this for these three schools and anticipates that may be some time in the future.
The department is currently progressing a range of legal and contractual mechanisms for recovering costs.
To ask the Secretary of State for Education, what estimate her Department has made of the total cost to the public purse of construction, demolition and reconstruction of school buildings constructed by Caledonian Modular and subsequently found to be structurally unsound.
To ask the Secretary of State for Education, what estimate her Department has made of the total cost to the public purse of construction, demolition and reconstruction of school buildings constructed by Caledonian Modular and subsequently found to be structurally unsound.
The department publishes contract values when available on Contracts Finder, which is available at: https://www.gov.uk/contracts-finder. In addition, the department publishes capital costs for all free schools on GOV.UK once all works are completed and costs are finalised. Once at that point, the department will action this for these three schools and anticipates that may be some time in the future.
The department is currently progressing a range of legal and contractual mechanisms for recovering costs.
To ask the Secretary of State for Education, what estimate her Department has made of the cost to the public purse of the (a) construction, (b) demolition and (c) reconstruction of buildings constructed by Caledonian Modular at (i) Haygrove School, (ii) Sir Frederick Gibberd College and (iii) Buckton Fields Primary...
To ask the Secretary of State for Education, what estimate her Department has made of the cost to the public purse of the (a) construction, (b) demolition and (c) reconstruction of buildings constructed by Caledonian Modular at (i) Haygrove School, (ii) Sir Frederick Gibberd College and (iii) Buckton Fields Primary...
The department publishes contract values when available on Contracts Finder, which is available at: https://www.gov.uk/contracts-finder. In addition, the department publishes capital costs for all free schools on GOV.UK once all works are completed and costs are finalised. Once at that point, the department will action this for these three schools and anticipates that may be some time in the future.
The department is currently progressing a range of legal and contractual mechanisms for recovering costs.
To ask His Majesty's Government which Government-funded construction projects had been awarded to Caledonian Modular prior to its collapse in March, including, for each project, the awarding department, the contract value, and the anticipated costs of remediation of defective work.
To ask His Majesty's Government which Government-funded construction projects had been awarded to Caledonian Modular prior to its collapse in March, including, for each project, the awarding department, the contract value, and the anticipated costs of remediation of defective work.
The Cabinet Office does not centrally hold commercial information on Government-funded construction projects. Individual departments manage and procure their own contracts. The Cabinet Office can confirm that no contracts with Caledonian Modular were held with the Cabinet Office prior to its collapse in March 2022.
To ask the Secretary of State for Education, how many school buildings constructed by (a) Caledonian Modular and (b) other contractors engaged under the Modern Methods of Construction framework have been investigated by her Department for possible safety defects; and if she will publish the findings of those investigations.
To ask the Secretary of State for Education, how many school buildings constructed by (a) Caledonian Modular and (b) other contractors engaged under the Modern Methods of Construction framework have been investigated by her Department for possible safety defects; and if she will publish the findings of those investigations.
Caledonian Modular Limited (CML) was directly contracted to deliver five schools by the Department for Education. The Department did not contract CML to build any further education college buildings. Three schools were completed and two were partially constructed and are being rebuilt.
All five of these schools delivered by CML have been investigated. No other schools using Modern Methods of Construction have been similarly investigated, and there are currently no plans to publish the findings.
Appropriate steps are being taken to enforce the Department’s contractual rights in relation to all affected CML schools, including those schools which have closed due to possible safety defects and those which never reached completion. The Department is pursuing all avenues for redress against the parties responsible for those issues.
To ask the Secretary of State for Education, whether her Department has taken steps to recover money from (a) the administrators of Caledonian Modular and (b) other organisations in relation to (i) schools that were never completed and (ii) schools constructed by Caledonian Modular that have since closed due to...
To ask the Secretary of State for Education, whether her Department has taken steps to recover money from (a) the administrators of Caledonian Modular and (b) other organisations in relation to (i) schools that were never completed and (ii) schools constructed by Caledonian Modular that have since closed due to...
Caledonian Modular Limited (CML) was directly contracted to deliver five schools by the Department for Education. The Department did not contract CML to build any further education college buildings. Three schools were completed and two were partially constructed and are being rebuilt.
All five of these schools delivered by CML have been investigated. No other schools using Modern Methods of Construction have been similarly investigated, and there are currently no plans to publish the findings.
Appropriate steps are being taken to enforce the Department’s contractual rights in relation to all affected CML schools, including those schools which have closed due to possible safety defects and those which never reached completion. The Department is pursuing all avenues for redress against the parties responsible for those issues.
To ask the Secretary of State for Education, how many (a) state-funded school and (b) college buildings were Caledonian Modular contracted to build by her Department since 2010; and whether she has an estimate on the number that were (i) completed and (ii) partially constructed.
To ask the Secretary of State for Education, how many (a) state-funded school and (b) college buildings were Caledonian Modular contracted to build by her Department since 2010; and whether she has an estimate on the number that were (i) completed and (ii) partially constructed.
Caledonian Modular Limited (CML) was directly contracted to deliver five schools by the Department for Education. The Department did not contract CML to build any further education college buildings. Three schools were completed and two were partially constructed and are being rebuilt.
All five of these schools delivered by CML have been investigated. No other schools using Modern Methods of Construction have been similarly investigated, and there are currently no plans to publish the findings.
Appropriate steps are being taken to enforce the Department’s contractual rights in relation to all affected CML schools, including those schools which have closed due to possible safety defects and those which never reached completion. The Department is pursuing all avenues for redress against the parties responsible for those issues.