To ask the Secretary of State for Defence, how much his Department has spent on the (a) upkeep and (b) maintenance of HMS Forth since 5 July 2024.
To ask the Secretary of State for Defence, how much his Department has spent on the (a) upkeep and (b) maintenance of HMS Forth since 5 July 2024.
The volume of detailed information requested is such that it will take time to consider in full. Consequently, I will write to the hon. Member and a copy of the letter will be placed in the Library of the House.
To ask the Secretary of State for Defence, when HMS Forth will be deployed; and whether it will be permanently deployed to the UK's South Atlantic Territories.
To ask the Secretary of State for Defence, when HMS Forth will be deployed; and whether it will be permanently deployed to the UK's South Atlantic Territories.
The Royal Navy maintains a permanent presence in the South Atlantic. For reasons of safeguarding national security, we do not discuss the detail of such operations or of future programmes, as this would or would be likely to prejudice the capability, effectiveness or security of the Armed Forces.
To ask the Secretary of State for Defence, when the Royal Navy officially accepted HMS Forth; when her sea trials commenced; and what the date is when sea trails are expected to be completed.
To ask the Secretary of State for Defence, when the Royal Navy officially accepted HMS Forth; when her sea trials commenced; and what the date is when sea trails are expected to be completed.
The Ministry of Defence accepted HMS Forth at Vessel Acceptance Date on 24 January 2018 and she was commissioned into the Royal Navy (RN) on 13 April 2018. Her contractor sea trials were conducted in two parts, in October 2017 and January 2018. The RN sea trials were conducted in January 2018.
HMS Forth will undertake further RN sea trials in the coming months with the expectation these will be completed in the summer.
To ask the Secretary of State for Defence, what estimate he has made of the cost to the public purse of the River Class 2 patrol vessel, HMS Forth (a) at inception and (b) when it was accepted by the Royal Navy.
To ask the Secretary of State for Defence, what estimate he has made of the cost to the public purse of the River Class 2 patrol vessel, HMS Forth (a) at inception and (b) when it was accepted by the Royal Navy.
The firm price contract for three River Class Offshore Patrol Vessels awarded to BAE Systems in August 2014 has a value of £378 million. The contract does not separately identify the cost of each of the three ships. Of the contract value, £30 million is for items including trials, spares, testing and Government Furnished Equipment. The value of the contract remains unchanged.
At contract award, the estimated build time of HMS Forth was 31 months. Delivery of the ship, in January 2018, was not in accordance with the planned schedule, owing to delays during construction. The build of HMS Forth was not affected by design, technical or relationship issues.
At contract award, the planned contract acceptance date for HMS Forth was May 2017. Contractor sea trials were expected to commence two months before contractual acceptance.
To ask the Secretary of State for Defence, what the estimated build time was for HMS Forth at inception; and whether that ship was delivered on time.
To ask the Secretary of State for Defence, what the estimated build time was for HMS Forth at inception; and whether that ship was delivered on time.
The firm price contract for three River Class Offshore Patrol Vessels awarded to BAE Systems in August 2014 has a value of £378 million. The contract does not separately identify the cost of each of the three ships. Of the contract value, £30 million is for items including trials, spares, testing and Government Furnished Equipment. The value of the contract remains unchanged.
At contract award, the estimated build time of HMS Forth was 31 months. Delivery of the ship, in January 2018, was not in accordance with the planned schedule, owing to delays during construction. The build of HMS Forth was not affected by design, technical or relationship issues.
At contract award, the planned contract acceptance date for HMS Forth was May 2017. Contractor sea trials were expected to commence two months before contractual acceptance.
To ask the Secretary of State for Defence, whether the build of HMS Forth was affected by (a) design problems, (b) technical issues or (c) relationship issues between the Royal Navy, Ministry of Defence and the contractor.
To ask the Secretary of State for Defence, whether the build of HMS Forth was affected by (a) design problems, (b) technical issues or (c) relationship issues between the Royal Navy, Ministry of Defence and the contractor.
The firm price contract for three River Class Offshore Patrol Vessels awarded to BAE Systems in August 2014 has a value of £378 million. The contract does not separately identify the cost of each of the three ships. Of the contract value, £30 million is for items including trials, spares, testing and Government Furnished Equipment. The value of the contract remains unchanged.
At contract award, the estimated build time of HMS Forth was 31 months. Delivery of the ship, in January 2018, was not in accordance with the planned schedule, owing to delays during construction. The build of HMS Forth was not affected by design, technical or relationship issues.
At contract award, the planned contract acceptance date for HMS Forth was May 2017. Contractor sea trials were expected to commence two months before contractual acceptance.
To ask the Secretary of State for Defence, at inception what the estimated hand over date of HMS Forth was; and when sea trials were expected to commence.
To ask the Secretary of State for Defence, at inception what the estimated hand over date of HMS Forth was; and when sea trials were expected to commence.
The firm price contract for three River Class Offshore Patrol Vessels awarded to BAE Systems in August 2014 has a value of £378 million. The contract does not separately identify the cost of each of the three ships. Of the contract value, £30 million is for items including trials, spares, testing and Government Furnished Equipment. The value of the contract remains unchanged.
At contract award, the estimated build time of HMS Forth was 31 months. Delivery of the ship, in January 2018, was not in accordance with the planned schedule, owing to delays during construction. The build of HMS Forth was not affected by design, technical or relationship issues.
At contract award, the planned contract acceptance date for HMS Forth was May 2017. Contractor sea trials were expected to commence two months before contractual acceptance.
To ask the Secretary of State for Defence, what the origin was of the steel cut for the hull of HMS Forth.
To ask the Secretary of State for Defence, what the origin was of the steel cut for the hull of HMS Forth.
The steel for HMS Forth (as well as HMS Medway and HMS Trent) is sourced via Dent Steel Services (Yorkshire), who conduct shot blasting and priming, from SSAB of Stockholm (previously 'Swedish Steel') who are able to supply the grade of steel necessary for this application.
To ask the Secretary of State for Defence, where his Department plans to base (a) HMS Forth, (b) HMS Medway and (c) HMS Trent.
To ask the Secretary of State for Defence, where his Department plans to base (a) HMS Forth, (b) HMS Medway and (c) HMS Trent.
The base-port of the three new Offshore Patrol Vessels, HMS Forth, HMS Medway and HMS Trent will be subject to the forthcoming Strategic Defence and Security Review.