To ask His Majesty's Government what the original estimated completion date was for the Beauly-Denny 400kV uprating project; and what the current estimated completion date is.
To ask His Majesty's Government what the original estimated completion date was for the Beauly-Denny 400kV uprating project; and what the current estimated completion date is.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Transmission Owners (TOs) are licensed and regulated by Ofgem. While TOs are responsible for delivering transmission projects, Ofgem plays a key role in scrutinising delivery plans, setting the regulatory requirements and monitoring performance (including completion dates), against agreed outputs and milestones. Ofgem holds TOs accountable for the efficient and timely delivery of network upgrades and can investigate potential non-compliance where delivery falls short of regulatory requirements.
To ask His Majesty's Government what the original estimated completion date was for the new 400kV double circuit Blackhillock-Peterhead project; and what the current estimated completion date is.
To ask His Majesty's Government what the original estimated completion date was for the new 400kV double circuit Blackhillock-Peterhead project; and what the current estimated completion date is.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Transmission Owners (TOs) are licensed and regulated by Ofgem. While TOs are responsible for delivering transmission projects, Ofgem plays a key role in scrutinising delivery plans, setting the regulatory requirements and monitoring performance (including completion dates), against agreed outputs and milestones. Ofgem holds TOs accountable for the efficient and timely delivery of network upgrades and can investigate potential non-compliance where delivery falls short of regulatory requirements.
To ask His Majesty's Government what the original estimated completion date was for the East Coast Onshore 400kV Phase 2 project; and what the current estimated completion date is.
To ask His Majesty's Government what the original estimated completion date was for the East Coast Onshore 400kV Phase 2 project; and what the current estimated completion date is.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Transmission Owners (TOs) are licensed and regulated by Ofgem. While TOs are responsible for delivering transmission projects, Ofgem plays a key role in scrutinising delivery plans, setting the regulatory requirements and monitoring performance (including completion dates), against agreed outputs and milestones. Ofgem holds TOs accountable for the efficient and timely delivery of network upgrades and can investigate potential non-compliance where delivery falls short of regulatory requirements.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the East Coast Onshore 400kV Phase 2 project.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the East Coast Onshore 400kV Phase 2 project.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Cost estimates are developed and maintained by the relevant Transmission Owners and are subject to regulatory scrutiny by Ofgem.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the new 400kV double circuit Blackhillock-Peterhead project.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the new 400kV double circuit Blackhillock-Peterhead project.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Cost estimates are developed and maintained by the relevant Transmission Owners and are subject to regulatory scrutiny by Ofgem.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the Beauly-Denny 400kV uprating project.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the Beauly-Denny 400kV uprating project.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Cost estimates are developed and maintained by the relevant Transmission Owners and are subject to regulatory scrutiny by Ofgem.
To ask His Majesty's Government what the original estimated completion date was for the Beauly-Loch Buidhe 400kV reinforcement project; and what the current estimated completion date is.
To ask His Majesty's Government what the original estimated completion date was for the Beauly-Loch Buidhe 400kV reinforcement project; and what the current estimated completion date is.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Transmission Owners (TOs) are licensed and regulated by Ofgem. While TOs are responsible for delivering transmission projects, Ofgem plays a key role in scrutinising delivery plans, setting the regulatory requirements and monitoring performance (including completion dates), against agreed outputs and milestones. Ofgem holds TOs accountable for the efficient and timely delivery of network upgrades and can investigate potential non-compliance where delivery falls short of regulatory requirements.
To ask His Majesty's Government what the original estimated completion date was for the Loch Buidhe-Spittal 400kV reinforcement project; and what the current estimated completion date is.
To ask His Majesty's Government what the original estimated completion date was for the Loch Buidhe-Spittal 400kV reinforcement project; and what the current estimated completion date is.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Transmission Owners (TOs) are licensed and regulated by Ofgem. While TOs are responsible for delivering transmission projects, Ofgem plays a key role in scrutinising delivery plans, setting the regulatory requirements and monitoring performance (including completion dates), against agreed outputs and milestones. Ofgem holds TOs accountable for the efficient and timely delivery of network upgrades and can investigate potential non-compliance where delivery falls short of regulatory requirements.
To ask His Majesty's Government what the original estimated completion date was for the new 400kV double circuit Beauly-Blackhillock project; and what the current estimated completion date is.
To ask His Majesty's Government what the original estimated completion date was for the new 400kV double circuit Beauly-Blackhillock project; and what the current estimated completion date is.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Transmission Owners (TOs) are licensed and regulated by Ofgem. While TOs are responsible for delivering transmission projects, Ofgem plays a key role in scrutinising delivery plans, setting the regulatory requirements and monitoring performance (including completion dates), against agreed outputs and milestones. Ofgem holds TOs accountable for the efficient and timely delivery of network upgrades and can investigate potential non-compliance where delivery falls short of regulatory requirements.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the Loch Buidhe-Spittal 400kV reinforcement project.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the Loch Buidhe-Spittal 400kV reinforcement project.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Cost estimates are developed and maintained by the relevant Transmission Owners and are subject to regulatory scrutiny by Ofgem.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the new 400kV double circuit Beauly-Blackhillock project.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the new 400kV double circuit Beauly-Blackhillock project.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Cost estimates are developed and maintained by the relevant Transmission Owners and are subject to regulatory scrutiny by Ofgem.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the Beauly-Loch Buidhe 400kV reinforcement project.
To ask His Majesty's Government what the (1) original, and (2) current, estimated cost is of the Beauly-Loch Buidhe 400kV reinforcement project.
Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Cost estimates are developed and maintained by the relevant Transmission Owners and are subject to regulatory scrutiny by Ofgem.
To ask His Majesty's Government what assessment they have made of the impact of electricity network connection delays on the delivery of artificial intelligence data centre developments.
To ask His Majesty's Government what assessment they have made of the impact of electricity network connection delays on the delivery of artificial intelligence data centre developments.
The Government recognises that growth in AI and data centres is increasing electricity demand and that grid connection delays are a major barrier to new capacity in the UK.
To address this, the Government is reforming the connections process to better support strategically important demand, including data centres. Working with DESNZ, Ofgem and the National Energy System Operator, reforms will reduce delays, limit speculative applications and prioritise viable projects, helping unlock capacity faster while maintaining security of supply. Through the AI Energy Council, co-chaired by the Secretaries of State for DBIST and DESNZ, DBIST is exploring resilient, sustainable and scalable.
Lords statement on allegations from whistleblowers within the National Energy System Operator regarding summer blackout risk.
Lords statement on allegations from whistleblowers within the National Energy System Operator regarding summer blackout risk.
I declare my interests as chair of Amey, Acteon and Buckthorn Partners. Can the Minister confirm the comments of whistleblowers that on 23 June
“constraints were breached and system security was compromised”—
and, I might add, five safety limits were breached as well? Can he confirm that such events can directly contribute...
I declare my interests as chair of Amey, Acteon and Buckthorn Partners. Can the Minister confirm the comments of whistleblowers that on 23 June
“constraints were breached and system security was compromised”—
and, I might add, five safety limits were breached as well? Can he confirm that such events can directly contribute...
The Government take the allegations that the whistleblowers have made recently concerning the operation of NESO very seriously. An external legal firm has been appointed to investigate, reporting to a panel independent of senior management; indeed, there is the opportunity for anybody independent of senior management to make representations to...
The Government take the allegations that the whistleblowers have made recently concerning the operation of NESO very seriously. An external legal firm has been appointed to investigate, reporting to a panel independent of senior management; indeed, there is the opportunity for anybody independent of senior management to make representations to...
My Lords, these allegations, if accurate, would represent a shocking breach of public trust by an organisation now owned directly by the Government. But it also demonstrates a failure of the current whistleblowing framework that, to be heard and to have some measure of protection, the whistleblower has had to...
My Lords, these allegations, if accurate, would represent a shocking breach of public trust by an organisation now owned directly by the Government. But it also demonstrates a failure of the current whistleblowing framework that, to be heard and to have some measure of protection, the whistleblower has had to...
As far as whistleblowing is concerned, I can speak only to this particular episode, but I point to the Government’s response—or, rather, the response of NESO and other bodies—in developing very rapidly a forum in which whistleblowers can confidentially and without any concerns about their own future or safety participate...
As far as whistleblowing is concerned, I can speak only to this particular episode, but I point to the Government’s response—or, rather, the response of NESO and other bodies—in developing very rapidly a forum in which whistleblowers can confidentially and without any concerns about their own future or safety participate...
My Lords, first, in welcoming my noble friend’s response, can he confirm that there was no loss of supply to customers on the occasion of the incidents referred to? Secondly, in response to the question from the noble Lord, Lord Moynihan, in which he attacked the Government’s investment in
wind...
My Lords, first, in welcoming my noble friend’s response, can he confirm that there was no loss of supply to customers on the occasion of the incidents referred to? Secondly, in response to the question from the noble Lord, Lord Moynihan, in which he attacked the Government’s investment in
wind...
Yes, that does make it very important that we continue decarbonising our energy systems to make sure that they are very resilient in a different climate that we will have in the future, and that the consequences of, for example, continuing to provide energy via high-carbon fossil fuels are countered...
Yes, that does make it very important that we continue decarbonising our energy systems to make sure that they are very resilient in a different climate that we will have in the future, and that the consequences of, for example, continuing to provide energy via high-carbon fossil fuels are countered...