To ask the Secretary of State for Transport, pursuant to the Answer of 3 November 2025 to Question 86345 on Whitchurch Station: Access, if she will announce the timeline for completion of Access for All construction at Whitchurch Railway Station.
To ask the Secretary of State for Transport, pursuant to the Answer of 3 November 2025 to Question 86345 on Whitchurch Station: Access, if she will announce the timeline for completion of Access for All construction at Whitchurch Railway Station.
We are committed to improving the accessibility of the railway and recognise the social and economic benefits this brings to communities.
Since 2006 the Access for All programme has installed accessible, step free routes at over 270 stations plus a range of smaller scale access improvements at around 1500 stations.
In May 2024, the previous government published a list of 50 additional stations selected for initial feasibility work, which included Whitchurch railway station.
Network Rail have now completed all 50 feasibility studies and we will shortly be announcing which of those stations will progress.
To ask the Secretary of State for Transport, pursuant to the Answer of 16 July 2025 to Question 67160 on Whitchurch Station: Access and with reference to the announcement on railway stations awarded Access for All accessibility funding, published on 24 May 2024, when she plans to announce the timeline...
To ask the Secretary of State for Transport, pursuant to the Answer of 16 July 2025 to Question 67160 on Whitchurch Station: Access and with reference to the announcement on railway stations awarded Access for All accessibility funding, published on 24 May 2024, when she plans to announce the timeline...
We are committed to improving the accessibility of the railway and recognise the social and economic benefits this brings to communities.
Since 2006 the Access for All programme has installed accessible, step free routes at over 270 stations plus a range of smaller scale access improvements at around 1500 stations.
In May 2024, the previous government agreed the publication of a list of 50 additional stations selected for initial feasibility work, which included Whitchurch railway station.
Network Rail have now completed all 50 feasibility studies and we will shortly be announcing which of those stations will progress.
That this House recognises the need for Whitchurch station to receive platform accessibility upgrades under the Department for Transport’s Access for All programme; expresses concern that disabled passengers, those with heavy luggage, small children or who are otherwise unable to traverse 44 steps, cannot access the station’s southbound platform or exit the station from trains travelling northbound; notes that Network Rail has designated the scheme at Whitchurch Station as high priority; further notes the detrimental impact that the lack of station access has on residents of Whitchurch and north Shropshire; and calls on the Government to confirm upgrades to Whitchurch station under the Access for All programme.
That this House recognises the need for Whitchurch station to receive platform accessibility upgrades under the Department for Transport’s Access for All programme; expresses concern that disabled passengers, those with heavy luggage, small children or who are otherwise unable to traverse 44 steps, cannot access the station’s southbound platform or...
The people of Whitchurch in my constituency will be quite pleased to see the response to my written question regarding the Access for All railway fund, which shows that £280 million has been allocated for the spending review period, but they will be really keen to know when we are...
The people of Whitchurch in my constituency will be quite pleased to see the response to my written question regarding the Access for All railway fund, which shows that £280 million has been allocated for the spending review period, but they will be really keen to know when we are...
I thank the hon. Member for raising the issue of step-free access at her local station—this issue is raised with me all the time at business questions. I am sure that a debate on the topic would be very well subscribed, if she wanted one, but I will ensure that...
I thank the hon. Member for raising the issue of step-free access at her local station—this issue is raised with me all the time at business questions. I am sure that a debate on the topic would be very well subscribed, if she wanted one, but I will ensure that...
To ask the Secretary of State for Transport, with reference to the announcement on railway stations awarded Access for All accessibility funding, published on 24 May 2024, what her planned timeline is for the completion of Access for All construction at Whitchurch Railway Station.
To ask the Secretary of State for Transport, with reference to the announcement on railway stations awarded Access for All accessibility funding, published on 24 May 2024, what her planned timeline is for the completion of Access for All construction at Whitchurch Railway Station.
This government is committed to improving the accessibility of the railway and recognises the social and economic benefits this brings to communities.
In May 2024, the previous government selected 50 stations for initial feasibility work for potential upgrades as part of our Access for All programme. This included Whitchurch railway station in Shropshire. We expect to provide an update to stakeholders during the summer.
To ask the Secretary of State for Transport, what recent progress she has made on (a) design finalisation, (b) contract award and (c) surveys for the Whitchurch step-free access project.
To ask the Secretary of State for Transport, what recent progress she has made on (a) design finalisation, (b) contract award and (c) surveys for the Whitchurch step-free access project.
This government is committed to improving the accessibility of the railway and recognises the social and economic benefits this brings to communities.
In May 2024, the previous government selected 50 stations for initial feasibility work for potential upgrades as part of our Access for All programme. This included Whitchurch railway station. We are in the early stages of understanding the full implications of the Spending Review for Access for All and other rail projects and will engage with stakeholders in due course.
To ask the Secretary of State for Transport, pursuant to the Answer of 20 March 2025 to Question 38692 on Whitchurch (Shropshire) Station: Access, when a decision on whether Whitchurch Station will proceed under the Access for All programme will be made.
To ask the Secretary of State for Transport, pursuant to the Answer of 20 March 2025 to Question 38692 on Whitchurch (Shropshire) Station: Access, when a decision on whether Whitchurch Station will proceed under the Access for All programme will be made.
This government is committed to improving the accessibility of the railway and recognises the social and economic benefits this brings to communities.
In May 2024, the previous government selected 50 stations for initial feasibility work for potential upgrades as part of our Access for All programme. This included Whitchurch railway station. We are in the early stages of understanding the full implications of the Spending Review for Access for All and other rail projects and will engage with stakeholders in due course.
To ask the Secretary of State for Transport, with reference to the Answer of (a) 24 July 2024 to Question 835 and (b) 25 November 2024 to Question 15073 on Whitchurch (Shropshire) Station: Access, what progress she has made on providing step-free access at Whitchurch Railway Station in Shropshire.
To ask the Secretary of State for Transport, with reference to the Answer of (a) 24 July 2024 to Question 835 and (b) 25 November 2024 to Question 15073 on Whitchurch (Shropshire) Station: Access, what progress she has made on providing step-free access at Whitchurch Railway Station in Shropshire.
Network Rail have completed an option selection report for step-free access at Whitchurch railway station. This will be reviewed alongside 49 other stations across Britain to determine which should progress.
To ask the Secretary of State for Transport, what plans she has to ensure step-free access to Whitchurch Railway Station.
To ask the Secretary of State for Transport, what plans she has to ensure step-free access to Whitchurch Railway Station.
The Government is committed to improving the accessibility of the railway and recognises the social and economic benefits this brings to communities.
Given the short time since the general election, I regret I am not yet able to comment on next steps regarding specific stations including Whitchurch station. We are carefully considering the best approach to the Access for All programme and we will provide updates to MPs and other stakeholders in due course.
To ask the Secretary of State for Transport, if he will take steps to provide step-free access at Whitchurch station in Shropshire.
To ask the Secretary of State for Transport, if he will take steps to provide step-free access at Whitchurch station in Shropshire.
Both myself and the Rail Minister are early in our tenure as transport Ministers. As such, we are yet to speak to Network Rail regarding the status of the Whitchurch station accessibility project. I look forward to discussing these proposals with Network Rail and other stakeholders in the near future.
To ask the Secretary of State for Transport, what recent steps her Department has taken with Network Rail to make Whitchurch railway station fully accessible.
To ask the Secretary of State for Transport, what recent steps her Department has taken with Network Rail to make Whitchurch railway station fully accessible.
As part of the Prime Minister’s Network North announcement, the Government confirmed £350m of additional funding will be made available to improve the accessibility of stations across Great Britain. We are assessing over 300 nominations for Access for All funding, including a nomination for Whitchurch railway station. If successful, the funding will create an obstacle free, accessible route from the station entrance to platforms. Successful nominations will be announced in due course.