Written question asked by Gerald Howarth (Conservative) on Tuesday, 18 October 2005, in the House of Commons. It was due for an answer on Thursday, 20 October 2005. It was answered by Adam Ingram (Labour) on Thursday, 3 November 2005 on behalf of the Ministry of Defence.
Warships
- Question
- To ask the Secretary of State for Defence what his latest estimate is of the cost of the (a) Swan Hunter-built vessels and (b) BAE Systems-built vessels which form part of the Landing Ships Dock (Auxiliary) project.
- Answer
-
[pursuant to the reply, 2 November 2005, Official Report, c.1073W]: The current contract values for the costs associated with the build of the Swan Hunter vessels is £236 million and £176 million for the BAE Systems vessels. In addition the Swan Hunter contract includes £62 million for the provision of Lead Yard Equipment and Services in support of the construction of the two BAE Systems ships, and £11 million for initial spares provisioning for all four ships. Both companies have indicated likely cost increases to their programmes, and as these are subject to commercial discussions between the Ministry of Defence and the companies, I am unable to give further details at this time.
Secondary information
- Type
- Written question
- Reference
- 20391; 438 c1264W;438 c1262W
- Session
- 2005-06
- Related items
-
Landing Ships Dock (Auxiliary) Programme
Friday, 11 November 2005
Written questions
House of Commons
- Subjects
- Procurement Warships
- Link
- View this Written question on www.publications.parliament.uk
Show all related items (6)
Librarians' tools
- Timestamp
- 2013-11-25 23:34:26 +0000
- URI
- http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1080160
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1080160
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1080160