Written question asked by Bernard Jenkin (Conservative) on Monday, 13 February 2006, in the House of Commons. It was due for an answer on Wednesday, 15 February 2006. It was answered by Stephen Ladyman (Labour) on Monday, 27 February 2006 on behalf of the Department for Transport.


A12 (Brentwood)

Question
To ask the Secretary of State for Transport what the contracted finish date was for the current stretch of road improvements on the A12 at Brentwood; and on what date they will be completed.
Answer

The contracted finish date for the road works on the A12 at Brentwood, otherwise known as the A12 Ingatestone scheme, was 8 March 2006.The expected finishing date is now 13 March 2006. This extra period of time includes four days, because the work took longer than the contractor planned and one day for delay due to changes that were ordered for the work.


Secondary information

Type
Written question
Reference
443 c146W;443 c146W; 52065
Session
2005-06
Subjects
Road works A12 Brentwood
Link
View this Written question on www.publications.parliament.uk