Oral question asked in the House of Lords, by Lord Berkeley (Labour). It was answered on Wednesday, 20 June 2007.


Railways: Paddington Crash

Question
My Lords, my noble and learned friend appears to suggest that the design of the layout outside Paddington was wrong. As my noble friend Lord Snape said, that was done by British Rail and approved by the Health and Safety Executive. Is not the situation a bit odd, given that after British Rail designed it and it came into operation, it was taken over by Railtrack, after which Network Rail took over responsibility when Railtrack failed? It is a long way from Network Rail accepting all the obligations and liabilities from Railtrack to the company being prosecuted for something that was done two predecessors ago.
Answer

My Lords, I repeat: the company accepted its responsibility for the liabilities that had been passed to it. It is not so much the design outside Paddington as the fact that the signal was for some reason obscured and not visible. No one really knows why the driver drove through that red light. There had been eight incidents in which attention had been drawn to drivers passing that signal at red. It ought to have been looked at and a new solution found, as it subsequently was when a system was put in place under which, if a driver passed that signal at red, the brakes would automatically come on. Had that system been in place then, this would never have happened.


Secondary information

Type
Oral question
Reference
693 c216 
Session
2006-07
Oral question type
Supplementary
Chamber / Committee
House of Lords chamber
Subjects
Accidents Prosecutions Public interest Railways Network Rail Ladbroke Grove
Link
View this Oral question on www.publications.parliament.uk