Armed Forces: Warships

Question
asked Her Majesty's Government:What were the contracted and out-turn prices and duration of refit for each of the Type 42 destroyers completed since 1997; and
Answer

There is no requirement to keep contractual information beyond seven years, and the costs of upkeep contracts that were completed prior to 2001 are no longer held. While details of upkeep contracts that were awarded following competition or under the SSS programme are provided in the following tables, it is not possible to provide complete details of contracts awarded through the allocated programme as some of the information is held in archive. Once this has been retrieved and analysed, I will write to the noble Lord with the requested information.

Competed contracts
HM Ship Type Refit dates Approx. duration (weeks) Contracted price (£m) ¹ Final cost (£m)
Gloucester T42 Feb 02-Apr 03 63 23.4 23.4
Argyll T23 Jun 03-Nov 03 24 5.6 5.6
Chatham T22 Jan 04-May 04 20 6.6 6.6
Manchester T42 Apr 04-Oct 04 28 6.9 6.6 ²
Lancaster T23 May 04-Dec 04 32 7.6 7.6
Somerset T23 May 06-Jun 07 56 11.9 11.9
Portland T23 May 06-Jan 07 44 8.7 8.7
Cornwall T22 Nov 04-Dec 05 56 13.4 13.4
Richmond T23 Aug 05-Sep 06 56 9.4 9.4
Kent T23 Jan 05-Jun 05 24 5.8 5.8

"¹ Out-turn cost data is not required for competed contracts as the price is agreed as part of the contract negotiations.""² The final cost for HMS Manchester was subject to implementation of a Target Cost Incentive Fee shareline, therefore cost underruns were shared between the MOD and the company." "² The final cost for HMS Manchester was subject to implementation of a Target Cost Incentive Fee shareline, therefore cost underruns were shared between the MOD and the company."

Contracts placed under the SSS Programme
HM Ship Type Refit dates Duration (weeks) Contracted price incl. profit and growth (£m) Out-turn cost excl. profit (£m) Final cost (£m)
Liverpool T42 Nov 06-Apr 07 22 5.6 Out-turn and final costs will not be available until final cost certificates have been submitted by the contractor
Cumberland T22 Dec 06-Feb 08 60 17.5
Iron Duke T23 Feb 07-Nov 07 40 10.8
Gloucester T42 May 07 Nov 07 30 6.4
St Albans T23 May 07-Jul 08 60 15.4

Secondary information

Type
Written question
Reference
705 c280WA; 6400
Session
2007-08
Related items
Deposited Paper DEP2009-0090
Tuesday, 13 January 2009
Deposited papers
House of Lords
Subjects
Contracts Costs Repairs and maintenance Warships Type 23 frigates Type 22 frigates Type 42 destroyers
Contains statistics
Yes
Link
View this Written question on www.publications.parliament.uk