Written question asked by Baroness Warsi (Conservative), in the House of Lords. It was answered by Lord Hunt of Kings Heath (Labour) on Monday, 20 April 2009.


Energy: Wyre Barrage

Question
To ask Her Majesty's Government what assessment they have made of a re-activation of the 1991 Wyre Tidal Barrage Scheme.
Answer

A 60-64 MW tidal barrage in the Wyre Estuary was covered in the Sustainable Development Commission's Turning the Tide report in October 2007. Officials from the Department of Energy and Climate Change met representatives of Wyre Tidal Energy Limited at the end of 2008 to discuss assessment of the feasibility of a project and the likely consenting requirements. DECC have maintained contact with the company, which is also a member of the newly formed Northwest Tidal Energy Group, supported by the Northwest Regional Development Agency, with which DECC officials have regular meetings. Tidal power schemes below 1 GW installed capacity would be eligible for a revenue subsidy of two renewables obligation certificates / MWh.


Secondary information

Type
Written question
Reference
2457; 709 c332-3WA
Session
2008-09
Subjects
Barrages Tidal power River Wyre