Written question asked by Lord Williams of Elvel (Labour), in the House of Lords. It was answered by Lord Shutt of Greetland (Liberal Democrat) on Monday, 27 September 2010.
Energy: Wind Turbines
- Question
- To ask Her Majesty’s Government whether they will continue to reimburse National Grid plc for its outlays in connecting inshore and offshore wind turbines to the England and Wales high voltage transmission network.
- Answer
-
The Government do not meet the cost of connecting renewable (or other) generation projects. Those costs are met by the charges paid by network users to National Grid under the supervision of Ofgem.
Secondary information
- Type
- Written question
- Reference
- 1915; 720 c439WA
- Session
- 2010-12
- Notes
- Answer received between Monday 2 August and Monday 9 August 2010.
- Subjects
- Finance Wind power National grid National Grid plc
- Link
- View this Written question on www.publications.parliament.uk
Librarians' tools
- Timestamp
- 2013-11-20 03:46:09 +0000
- URI
- http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1544707
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1544707
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1544707