Written question asked by Greg Knight (Conservative) on Tuesday, 13 March 2012, in the House of Commons. It was due for an answer on Thursday, 15 March 2012. It was answered by Mike Penning (Conservative) on Tuesday, 20 March 2012 on behalf of the Department for Transport.


M1: Repairs and Maintenance

Question
To ask the Secretary of State for Transport when she expects all roadworks and lane closures to be completed on the M1 between London and its junction with the M6; and if she will make a statement.
Answer

The following road works are currently on or expected to start on the M1 between London and its junction with the M6. Their expected completion dates are as shown in the following table.

Expected completion date Scheme Nature of work
Spring 2013 M1 J10-13 Improvement Implementation of Dynamic Hard Shoulder running with improvements to junctions 11 and 12 and additional maintenance works where required.
May 2013 M1 J19Catthorpe Viaduct Viaduct replacement—current structure at end of life.
18 April 2012 M1 North of J17 (Southbound) Drainage and subsidence works.
30 April 2012 M1 J17-J16 (Southbound) Barrier renewal.
25 March 2012 M1 J17-18 (Northbound) Barrier Renewal.
25 March 2012 M1 North of Junction 16 Drainage and subsidence works.
27 March 2012 M1 between Junctions 18-20 Safety work (white line and stud renewal) due to start on 19 March 2012.
29 June 2012 M1 between Junctions 12 and 13 Bridge parapet renewals due to start on 2 April 2012.

Secondary information

Type
Written question
Reference
100413; 542 c613W
Session
2010-12
Subjects
Repairs and maintenance M1
Link
View this Written question on www.publications.parliament.uk