Written question asked by Harry Cohen (Labour) on Monday, 29 November 1999, in the House of Commons. It was due for an answer on Tuesday, 7 December 1999. It was answered by Keith Hill (Labour) on Tuesday, 7 December 1999 on behalf of the Department of the Environment, Transport and the Regions.


Dept of the Environment Transport and the Regions

Question
To ask the Secretary of State for the Environment, Transport and the Regions, how many miles of high-tension and control cables (a) have been and (b) will be transferred to the Seeboard Powerlink consortium under the Power PFI contract. - Includes figure.
Answer

Mr. Cohen: To ask the Secretary of State for the Environment, Transport and the Regions how many miles of high-tension and control cables (a) have been and (b) will be transferred to the Seeboard Powerlink consortium under the Power PFI contract. [100932] Mr. Hill: Under the terms of the Power PFI contract, approximately 1,000 miles each of high-tension and control cables (covering the entire Underground network) transferred to Seeboard Powerlink on 16 August 1998. Seeboard Powerlink is responsible for the maintenance and renewal of these cables for the duration of the contract.


Secondary information

Type
Written question
Reference
340 c478-9W; 100932
Session
1999-00
Subjects
Electricity generation Electricity Electric cables Private finance initiative London Underground Powerlink