Skip to main content

Written question asked by Robert Key (Conservative) on Wednesday, 21 June 2000, in the House of Commons. It was due for an answer on Monday, 26 June 2000. It was answered by Lord Moonie (Labour) on Monday, 26 June 2000 on behalf of the Ministry of Defence.


Ministry of Defence

Question
To ask the Secretary of State for Defence, if he will list (a) the original in-service date, (b) the current in-service date, (c) the actual or estimated cost, (d) the years of peak expenditure, (e) the expenditure in (d), (f) the date of the initial gate, (g) the date of the main gate and (h) the prime contractor for the projects (i) BOWMAN, (ii) COBRA, (iii) FET, (iv) HARRV, (v) MRAV, (vi) Phoenix, (vii) Shielder and (viii) UK Attack Helicopter; if he will list (a) the original in-service date, (b) the current in-service date, (c) the actual or estimated cost, (d) the years of peak expenditure, (e) the expenditure in (d), (f) the date of the initial gate, (g) the date of the main gate and (h) the prime contractor for the projects (i) ASRAAM, (ii) ASTOR, (iii) BVRAAM, (iv) Brimstone, (v) Eurofighter, (vi) FCBA, (vii) FGBAD, (viii) FOAS, (ix) FSTA, (x) Hercules Rolling Replacement Tranche 2, (xi) Merlin HM Mk1, (xii) Merlin HC Mk3, (xiii) Nimrod MRA-4, (xiv) STSA, (xv) CASOM and (xvi) SABR; if he will list (a) the original in-service date, (b) the current in-service date, (c) the actual or estimated cost, (d) the years of peak expenditure, (e) the expenditure in (d), (f) the date of the initial gate, (g) the date of the main gate and (h) the prime contractor for the projects (i) Astute Class Submarines, (ii) CV(F), (iii) FASGW, (iv) FCBA, (v) LPD(R) and (vi) MCMU. - Will write.
Answer

Mr. Key: To ask the Secretary of State for Defence (1) if he will list (a) the original in-service date, (b) the current in-service date, (c) the actual or estimated cost, (d) the years of peak expenditure, (e) the expenditure in (d), (f) the date of the initial gate, (g) the date of the main gate and (h) the prime contractor for the projects (i) BOWMAN, (ii) COBRA, (iii) FET, (iv) HARRV, (v) MRAV, (vi) Phoenix, (vii) Shielder and (viii) UK Attack Helicopter; [127707] (2) if he will list (a) the original in-service date, (b) the current in-service date, (c) the actual or estimated cost, (d) the years of peak expenditure, (e) the expenditure in (d), (f) the date of the initial gate, (g) the date of the main gate and (h) the prime contractor for the projects (i) ASRAAM, (ii) ASTOR, (iii) BVRAAM, (iv) Brimstone, (v) Eurofighter, (vi) FCBA, (vii) FGBAD, (viii) FOAS, (ix) FSTA, (x) Hercules Rolling Replacement Tranche 2, (xi) Merlin HM Mk1, (xii) Merlin HC Mk3, (xiii) Nimrod MRA-4, (xiv) STSA, (xv) CASOM and (xvi) SABR; [127708] (3) if he will list (a) the original in-service date, (b) the current in-service date, (c) the actual or estimated cost, (d) the years of peak expenditure, (e) the expenditure in (d), (f) the date of the initial gate, (g) the date of the main gate and (h) the prime contractor for the projects (i) Astute Class Submarines, (ii) CV(F), (iii) FASGW, (iv) FCBA, (v) LPD(R) and (vi) MCMU. [127706] Dr. Moonie: I will write to the hon. Member and a copy of my letter will be placed in the Library of the House.


Secondary information

Type
Written question
Reference
352 c413-4W; 127707;127708;127706
Session
1999-00
Subjects
Deployment Defence equipment Expenditure Procurement
Link
View this Written question on www.publications.parliament.uk