Skip to main content

Written question asked by Mike Hancock (Liberal Democrat) on Tuesday, 29 January 2002, in the House of Commons. It was due for an answer on Friday, 1 February 2002. It was answered by Lord Moonie (Labour) on Friday, 1 February 2002 on behalf of the Ministry of Defence.


Ministry of Defence

Question
To ask the Secretary of State for Defence, how much the series of improved software releases to enhance MBDA's advanced short-range air-to-air missile will cost; when the final improved software releases are expected to be completed; and if he will make a statement.
Answer

Mr. Hancock: To ask the Secretary of State for Defence how much the series of improved software releases to enhance MBDA's advanced short-range air-to-air missile will cost; when the final improved software releases are expected to be completed; and if he will make a statement. [32156] Dr. Moonie: The cost of the additional software releases to achieve ASRAAM's Full Operational Capability will be borne by the contractor, MBDA UK Ltd. (formerly Matra BAe Dynamics), and is a matter for them. The company's aim is to deliver the required missile performance by the end of 2003. If that is not achieved, our agreement with MBDA Uk allows for a further software release.


Secondary information

Type
Written question
Reference
32156; 379 c601W;379 c597W
Session
2001-02
Subjects
Software Standards Antiaircraft missiles
Link
View this Written question on www.publications.parliament.uk