Written question asked by Dominic Grieve (Conservative) on Thursday, 19 March 2015, in the House of Commons. It was due for an answer on Monday, 23 March 2015. It was answered by Robert Goodwill (Conservative) on Wednesday, 25 March 2015 on behalf of the Department for Transport.


High Speed 2 Line

Question

To ask the Secretary of State for Transport, what recent estimate his Department has made of the cost of construction of the proposed tunnel for High Speed 2 from Old Oak Common to Euston.

Answer

The estimated cost of construction for the proposed tunnel for High Speed 2 from Old Oak Common to Euston is £434m. This costs figure (which is based on Q2 2011 prices) includes construction of the associated shafts and portals, but excludes land and property costs.


Secondary information

Type
Written question
Reference
228474
Session
2014-15
Subjects
Costs High Speed 2 line
Contains statistics