Written question asked by Keir Starmer (Labour) on Friday, 2 September 2016, in the House of Commons. It was due for an answer on Tuesday, 6 September 2016. It was answered by Andrew Jones (Conservative) on Thursday, 8 September 2016 on behalf of the Department for Transport.
High Speed 2 Line: Euston Station
- Question
-
To ask the Secretary of State for Transport, pursuant to the Answer of 5 July 2016 to Question 41593, when the additional works on passenger train impacts from any transportation of excavated and construction materials at Euston is planned to be completed.
- Answer
-
The detailed timetable for this work is being developed with Network Rail. However, we would hope that it would be complete in early 2017. This work will be undertaken in close dialogue with the Greater London Authority, London Borough of Camden and Transport for London.
Secondary information
- Type
- Written question
- Reference
- 44619
- Session
- 2016-17
- Related items
- Subjects
- Construction High Speed 2 line Euston Station
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2021-12-31 22:29:44 +0000
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2016-17/44619
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2016-17/44619
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2016-17/44619