Written question asked by Cheryl Gillan (Conservative) on Tuesday, 3 July 2018, in the House of Commons. It was due for an answer on Friday, 6 July 2018 (named day). It was answered by Nusrat Ghani (Conservative) on Friday, 6 July 2018 on behalf of the Department for Transport.


High Speed 2 Line: Chilterns

Question

To ask the Secretary of State for Transport, whether the tunnelling of High Speed Two under the Chilterns is planned to involve Bentonite under pressure.

Answer

The operation of the Chiltern tunnel Tunnel Boring Machine will not use bentonite. As HS2 Ltd have always made clear, they will not begin works in the area until the Environment Agency is satisfied with their final approach.

However, it is currently proposed that Bentonite will be used in the construction of the diaphragm walls for the 5 intermediate shafts. Prior to the use of bentonite in these locations the construction methodology dictates that the ground surrounding the diaphragm walls will be grouted, therefore sealing and protecting the ground water from the bentonite.


Secondary information

Type
Written question
Reference
160054
Session
2017-19
Related items
High Speed 2 Line
Monday, 13 July 2020
Written questions
House of Commons
Subjects
Construction Tunnels High Speed 2 line Chilterns Clay
Link
View this Written question on www.parliament.uk