Written question asked by Anneliese Dodds (Labour) on Monday, 3 December 2018, in the House of Commons. It was due for an answer on Thursday, 6 December 2018 (named day). It was answered by Stuart Andrew (Conservative) on Thursday, 6 December 2018 on behalf of the Ministry of Defence.


AWE

Question

To ask the Secretary of State for Defence, with reference to the Answer of 15 December 2015 to Question 20228 on AWE, what his most recent estimate is of the (a) anticipated out-turn cost and (b) projected in-service date of each of the new build projects in the Atomic Weapons Establishment Site Development Context Plan.

Answer

The tables below show the approved costs and in-service dates of the new build projects listed in the Atomic Weapons Establishment Site Development Context Plan (SDCP).

In-service dates are shown in bandings to avoid prejudice to national security and defence. Costs for planned projects are subject to approval.

Table 1 – Approved new build projects.

Ongoing projects

Function

In-Service Period

Approved cost

Warhead assembly/disassembly – Mensa

Manufacturing/ production

2023

£1.8 billion

Uranium components – Pegasus

Manufacturing/ production

Requirement under consideration

£634 million

Table 2 – Planned projects not yet approved.

Ongoing projects

Function

In-Service Period

Salts Processing - Octans

Testing/research

2020-25

Initiator system manufacture-Taurus

Manufacturing/production

2025-30

Large Scale formulations-Scorpius

Manufacturing/production

2030-40

Depleted Uranium Facility

Manufacturing/production

2020-25

Assembly for Trials-Columba

Testing/research

2030-35

High Explosive Climatic Trials

Testing/research

2030-35

Four of the projects previously listed are no longer included, as it is now planned to use the existing facilities. These are Small Scale Formulations (Cepheus), New Plutonium Facility, Non-Metallics and Materials (Libra) and Chemical Processing (Astra).

Planned new build projects now also include the Hub, a testing/research facility to be brought into service over the period 2020 – 2025.


Secondary information

Type
Written question
Reference
198373
Session
2017-19
Related items
AWE
Wednesday, 23 December 2015
Written questions
House of Commons
AWE
Thursday, 24 February 2022
Written questions
House of Commons
Subjects
Costs AWE
Contains statistics
Yes
Link
View this Written question on www.parliament.uk