Written question asked by Anna Soubry on Thursday, 27 June 2019, in the House of Commons. It was due for an answer on Monday, 1 July 2019. It was answered by Nusrat Ghani (Conservative) on Tuesday, 2 July 2019 on behalf of the Department for Transport.


High Speed 2 Line: Toton

Question

To ask the Secretary of State for Transport, whether he has made an estimate of the costs of constructing an underground High Speed Two East Midlands hub station at Toton Sidings.

Answer

Some of the tunnel options that have been looked at in the East Midlands Hub area included variants of a station, both at grade and below ground. Tunnel options in this area have not been progressed due to the significant length of the tunnel, significant cost impacts and flood risk. HS2 Ltd continues to refine the station design, taking into consideration the environment, cost and views of local stakeholders. The current station proposal has been well received by local leaders across the region.


Secondary information

Type
Written question
Reference
270337
Session
2017-19
Subjects
Costs Construction Railway stations High Speed 2 line Toton
Contains statistics
Yes
Link
View this Written question on www.parliament.uk